Which of the following is a PRINCE2 principle?
A. A project has defined and agreed roles and responsibilities
B. The customer will specify the desired result
C. The supplier will supply the resources to deliver the required result
D. Every project will need a different project management approach
正解:A
質問 2:
What is the name given to the individual assigned to carry out a risk response action or actions to respond to a particular risk or set of risks?
A. Risk Manage
B. Risk Actionee
C. Risk Owner
D. Risk Coordinator
正解:B
質問 3:
Which of the following Plans can be approved by the Project Manager?
A. Exception Plan at stage-level
B. Project Plan
C. Stage Plan
D. Team Plan
正解:D
質問 4:
Which of the following management levels sits outside the project management team, but will be responsible for commissioning a project?
A. Delivering
B. Managing
C. Directing
D. Corporate or programme management
正解:D
質問 5:
Where would a Team Manager find information regarding the specific quality required for a product?
A. Quality Management Strategy
B. Checkpoint Report
C. Quality Register
D. Product Description
正解:D
質問 6:
Which of the following is FALSE regarding PRINCE2 principles?
A. A project should have a customer/supplier environment
B. A project should be tailored to suit the project environment
C. A project should focus on products
D. A project should manage by exception
正解:A
質問 7:
According to PRINCE2, Project Board members would NOT be involved in which of the following?
A. Authorizing the start of the project
B. Communications between the project management team and stakeholders external to that team
C. Confirming project tolerances with corporate or programme management
D. Running of the project on a day-to-day basis
正解:D
绪川** -
10日前に購入して問題を全部覚えて行って、ようやく合格することができました。Pass4Testさんに感謝です。