Which is a responsibility of the Project Assurance role?
A. Ensure the Project Manager is aware of the need to use any existing corporate standards
B. Inform the Project Manager about the status of the project's products
C. Document the Project Board's reporting needs
D. Inform corporate or programme management about the project's status
正解:B
質問 2:
Which of the following is a Project Board control?
A. Use of project registers and logs to review progress
B. Approving a deviation of benefits tolerance
C. Approve a Plan, with its relevant tolerances for the next management stage
D. Review Checkpoint Reports to monitor progress
正解:C
質問 3:
Which role has a specific responsibility for referring to the Project Board if any delegated limits of authority or allocated change budget are forecast to be exceeded?
A. Project Assurance
B. Change Authority
C. Team Manager
D. Project Manager
正解:B
質問 4:
If a product's weight was specified to be 300 grams but could only be built to a weight of 400 grams, which of the following would be created?
A. Exception Plan
B. Off-specification
C. Request for change
D. Exception Report
正解:B
質問 5:
What is a purpose of the Project Product Description?
A. Provides input to the creation of the project mandate
B. Describes what the project has to produce to obtain customer acceptance
C. Provides a reference to find out what the project is about and how it is being managed
D. Defines the reporting structure to be used by the project
正解:B
質問 6:
Which role is responsible for specifying the benefits and for ensuring that they are subsequently realized?
A. Executive
B. Project Assurance
C. Senior User
D. Project Manager
正解:C
質問 7:
Which process would check and accept Work Packages?
A. Controlling a Stage
B. Managing Product Delivery
C. Directing a project
D. Managing a Stage Boundary
正解:B