At the end of PI Planning after dependencies are resolved and risks are addressed, a confidence vote is taken.
What is the default method used to vote?
A. Participatory Voting
B. WSJF
C. Fist of Five
D. Estimation Poker
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
The Program Board shows which two items? (Choose two)
A. Epics
B. Significant dependencies
C. Stories
D. Features
E. Capacity and load
正解:B,D
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Which statement is a value from the Agile Manifesto?
A. Customer collaboration over a constant indefinite pace
B. Customer collaboration over contract negotiation
C. Customer collaboration over ongoing internal conversation
D. Customer collaboration over individuals and interactions
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
What else does the SAFe principle, unlock the intrinsic motivation of knowledge workers, require besides purpose and minimum possible constraints?
A. Innovation
B. Autonomy
C. Transparency
D. Incentive-based compensation
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
When basing decisions on economics, how are lead time, product cost, value, and development expense used?
A. To recover money already spent
B. To understand solution tradeoffs
C. To limit work in process (WIP)
D. To take into account sunk costs
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
During the PI Planning event, when are planning adjustments agreed upon?
A. During the management review and problem-solving
B. During Scrum of Scrums
C. During the draft plan review
D. During breakout sessions
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
During the final plan review, Program risks are addressed using ROAM. What do the letters in ROAM represent?
A. Ratified, Offered, Activated, Maximized
B. Resolved, Owned, Accepted, Mitigated
C. Rectified, Omitted, Allocated, Mastered
D. Recorded, Ordered, Assigned, Moved
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
Which SAFe Lean-Agile Principle includes the critical part of "delaying decisions to the last responsible moment"?
A. Assume variability; preserve options
B. Build incrementally with fast, integrated learning cycles
C. Make value flow without interruptions
D. Base milestones on objective evaluation of working systems
正解:A