Identify the missing words in the following sentence.
The 'starting up a project" process is triggered when a [ ? J is available.
A. project mandate
B. stage plan
C. work package
D. project business case
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
What is the first task of product-based planning?
A. Create the product breakdown structure
B. Produce the Initiation Stage Plan
C. Write the Project Product Description
D. Identify dependencies
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Which are purposes of the quality theme?
1. To implement continuous improvement during the project
2. To establish how the project will ensure that products created will be acceptable to key stakeholders
3. To ensure that the project is desirable and achievable
4. To identify, assess and control uncertainty
A. 3 and 4
B. 1 and 2
C. 2 and 3
D. 1 and 4
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Which is an objective of the Closing a Project process?
A. Perform any post-project reviews
B. Create a Benefits Review Plan
C. Review the performance of the project against its baseline
D. Review and approve the plan for project closure
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
What should the benefits management approach define?
A. How the project has progressed against its plans
B. What will be used to record the effectiveness of the project's approaches
C. The suitability of the project management team structure
D. What actions will be taken to ensure the project's outcomes are achieved
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
Which management product is used to record relationships between specialist products?
A. Change control approach
B. Issue register
C. Product status account
D. Configuration item record
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
From whom does a Team Manager obtain approval for a completed product?
A. Project Support
B. Senior Supplier
C. The authority defined in the Product Description
D. Project Manager
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
A. Decide
B. Capture
C. Examine
D. Propose
正解:C
解説: (Pass4Test メンバーにのみ表示されます)