Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?
A. Manage by stages
B. Manage by exception
C. Continued business justification
D. Defined roles and responsibilities
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Which is one of the three levels of plan in PRINCE2?
A. Programme Plan
B. Benefits Review Plan
C. Team Plan
D. Project Brief
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
How does the 'managing product delivery' process achieve its purpose?
A. By agreeing requirements for how project work should be undertaken
B. By escalating issues and risks that cannot be resolved within stage tolerance
C. By producing highlight reports to enable the project board to oversee the work
D. By requiring the project manager to produce and monitor team plans
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.
A. project budget
B. project's risk tolerance
C. project's cost tolerance
D. change budget
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?
A. To identify uncertainties that may impact on the delivery of the project objectives
B. To identify the roles to be involved in risk management activities
C. To identify information about the project environment and objectives
D. To identify responses to risks documented in the business case
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
Which is definition of culture?
A. An essential aspect of project management that needs to be continually addressed
B. The tailoring required to take into account the complexity or simplicity of a project
C. The set of shared attitudes, values, goals, and ways of working that characterize a group of people
D. The process when people from across the project ecosystem work together
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
Which product identifies the management stages and timescales of a project?
A. Project Product Description
B. Project Plan
C. Initiation Stage Plan
D. Project Brief
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
How is Uncertainty Identified, assessed and controlled?
A. By analysing the risk cause in detail
B. By applying the risk practice
C. By avoiding or reducing a threat
D. By allocating a risk budget to the project
正解:B
解説: (Pass4Test メンバーにのみ表示されます)