The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
A. Executing.
B. Initiating,
C. Monitoring and Controlling.
D. Planning.
正解:C
質問 2:
The person assigned by the performing organization to be responsible for achieving the project objectives is the:
A. program manager
B. portfolio manager
C. project manager
D. functional manager
正解:B
質問 3:
In a weak matrix, the project managers role is:
A. part-time
B. occasional
C. full-time
D. unlimited
正解:A
質問 4:
The process of identifying specific actions to be performed to produce project deliverables is:
A. Create WBS.
B. Define Scope.
C. Define Activities.
D. Develop Schedule.
正解:C
質問 5:
The project manager for XYZ stationers is sequencing the activities for the project to set up a new office. It is known from knowledge of best practices that it is better to wait for the painters to finish painting the walls before the new floors are installed. This is an example of which of the following types of dependency?
A. Precedence
B. Mandatory
C. Discretionary
D. External
正解:C
質問 6:
Portfolio Management is management of:
A. all projects undertaken by a company.
B. a project by dividing the project into more manageable sub-projects.
C. a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.
D. a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.
正解:C
質問 7:
Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?
A. Inspection
B. Project analysis
C. Document analysis
D. Decomposition
正解:D
質問 8:
A tool or technique used in the Control Procurements process is:
A. Performance reporting.
B. Reserve analysis.
C. Bidder conferences.
D. Expert judgment.
正解:A
質問 9:
What are the five Project Management Process Groups?
A. Introduction, Planning, Implementation, Monitoring and Controlling, and Closure
B. Introduction, Planning, Executing, Monitoring and Controlling, and Closing
C. Initiating, Planning, Executing, Monitoring and Controlling, and Ending
D. Initiating, Planning, Executing, Monitoring and Controlling, and Closing
正解:D