You are the project manager for your organization. You and the project team are developing the project schedule for your current project. This project management process will create four outputs. Which of the following is an output of the Develop Schedule process?
A. Schedule baseline
B. Resource calendars
C. Work performance information
D. Activity duration estimates
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario?
A. Analogous estimate
B. Bottom-up estimate
C. Definitive estimate
D. Parametric estimate
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of which are external to her organization. In this project, Anna wants to create a method to classify the stakeholders based on their level of authority and their level of concern regarding the project outcomes. This model will help Anna determine the communication demands and when information should be distributed. What does Anna want to create in this instance?
A. Communications matrix
B. Salience model
C. Power/influence grid
D. Power/interest grid
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Which of the following group activity techniques allows a large number of ideas to be sorted into groups for review and analysis?
A. Nominal group technique
B. Delphi technique
C. Idea/mind mapping
D. Affinity diagram
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?
A. Integrated change control
B. Scope change control
C. Change Control Board approval process
D. Schedule change control
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?
A. Rolling wave plan
B. Decomposition
C. Templates
D. Precedence diagramming method
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
Michelle works as a scheduler in Array Inc. She has to create a schedule for a project assigned to her. Choose and reorder the steps that she should follow while creating the schedule for the project. Select an item from the right pane. Click button to move the selected item to the left pane. Click button to move the item back to the right pane. Click and buttons to sort the list, if required.

正解:

Explanation:
Schedule development is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. Inserting the activities, durations, and resources into the scheduling tool generates a schedule with planned dates for completing the project activities. The goal of the schedule development is to form the processes such that the stakeholders can use it in the creation of the project. Schedule development consists of two main sections: 1. Input and Data: The starting point for any schedule is the input of information developed during the planning process. Define schedule scope Breakdown structure relationships Schedule specification
Feedback from stakeholders Cost estimate model
2. Creating Schedule: This process provides basic knowledge in an outline structure for a study of the means, methods, and tools necessary for the project schedule development process. Types of schedules Activities Durations Relationships Constraints and calendars Cost and resource loading Schedule quality analysis and compliance review Schedule basis documentation
質問 8:
Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer?
A. Project charter
B. Scope of statement
C. SOW
D. WBS
正解:C
解説: (Pass4Test メンバーにのみ表示されます)