Gary is the project manager for his organization. The projects that Gary manages for project customers are often very similar in nature so Gary uses a schedule network template to help plan the project work. For Gary's current project, he has used a network template that includes just a portion of the project work adapted to the current project. When Gary uses a portion of a network template diagram this is called what term?
A. Analogous
B. Parametric
C. Hanger
D. Fragment network
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Joseph works as the project manager of the NHQ Project. He has created the project network diagram as shown in the figure: critical path. These results allow managers to prioritize activities for the effective management of project completion, and to shorten the planned critical path of a project by pruning critical path activities, by "fast tracking" (i.e., performing more activities in parallel), and/or by "crashing the critical path" (i.e., shortening the durations of critical path activities by adding resources). Answer option A is incorrect. ABEHJ takes only 22 days to complete. ABEHJ= A(4)+B(5)+E(2)+H(7)+J(4)= 22 Answer option C is incorrect. ABDHJ takes 21 days to complete. ABDHJ= A(4)+B(5)+D(1)+H(7)+J(4)= 21 Answer option B is incorrect. ABDIJ takes 21 days to complete. ABDIJ= A(4)+B(5)+D(1)+I(7)+J(4)= 21

Based on the network diagram, find out which path is the critical path for this project?
A. ABDHJ
B. ACFIJ
C. ABEHJ
D. ABDIJ
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and she needs to express to her project team and to the management the importance of communication in this project. She would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?
A. 78
B. 3,003
C. 6,084
D. 156
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
You are the project manager of the MQQ project. Unfortunately, this project is not performing well and you must do something to address the problems in your project. Based on your planning for monitoring and controlling project performance, you know that there are three outputs of performance reporting. Which one of the following is the only output that is most appropriate for this poorly performing project?
A. Change requests
B. Performance reports
C. Organizational process assets update
D. Performance re-baselining
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
John is the project manager for his organization. He has created a status dashboard for his stakeholders. What is a status dashboard?
A. It is a report that details the current status of risks and issues.
B. It is a report that reflects the overall performance of scope, schedule, quality, cost, or other project performance metrics.
C. It is a software application that allows stakeholders to view the project manager's performance.
D. It is a web-based tool to inspect the project deliverables for performance.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
Ned is the project manager for his organization. Ned is using a standard tool to capture, store, and distribute information to the stakeholders about the project costs, schedule, and performance. What term is assigned to this communication tool?
A. Table reporting
B. Communications management system
C. Reporting system
D. Project management information system
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?
A. Estimate activity resources
B. Estimate activity durations
C. Develop schedule
D. Control schedule
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will you record for this activity?
A. 48
B. 20o, 45m, 90p
C. 90
D. 45
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 9:
You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special hardware to electronically lock and open the doors. You've gathered the project team before they begin the installation for a hands-on training. As a group you and the project team install 50 doors following a checklist of instructions so that every door will be installed exactly the same throughout the campus and with minimal waste. This is an example of what project execution technique?
A. Implemented corrective action
B. Quality control
C. Preventive action
D. Defect repair validation
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
Fujisaki -
PMI-SP問題集のおかげで、PMI-SP試験に合格しました。PMI-SP問題集も私の仕事に役に立ちます。