Exhibit:

Look at the diagram. This daily backup job has been running for over 30 days and no active full backups have been taken since the first run. Which of the following best describes the backup job?
A. This is a forward incremental backup with transform enabled, keeping four restore points
B. This is a reverse incremental backup, keeping seven restore points
C. This is forever forward incremental backup, keeping seven restore points
D. This is a forward incremental backup with Sunday and Wednesday synthetic full, keeping seven restore points
正解:B
質問 2:
Which of the following predefined tests can be performed during a SureBackup verification test on a backup file? (Choose three.)
A. Application test
B. OS test
C. Heartbeat test
D. SAN check
E. Ping test
F. Boot time
正解:A,C,E
質問 3:
A company has the following requirements:
Mission-critical VMs: hourly replication to disaster recovery site, daily backups of these VMs should be available at the disaster recovery site when required, the mission critical applications need to be available within 20 minutes.
Business-important VMs: daily backups should be stored at the disaster recovery site. When required, the business-important applications need to be available within four hours.
Define the RPO and RTO for the company's disaster recovery site.
A. Mission-critical VMs: RPO = 60 minutes, RTO = 20 minutes; business-important VMs: RPO = 24 hours, RTO = four hours
B. Mission-critical VMs: RPO = 60 minutes, RTO = one hour; business-important VMs: RPO = 60 minutes, RTO = four hours
C. Mission-critical VMs: RPO = 24 hours, RTO = 20 minutes; business-important VMs: RPO = 24 hours, RTO
= four hours
D. Mission-critical VMs: RPO = 24 hours, RTO = four hours; business-important VMs: RPO = 24 hours, RTO = four hours
正解:A
質問 4:
If you need to run a script to stop a service in order to get an application-consistent backup on a Windows server, where can the script be run?
A. In the guest processing setting of the job, enable application-aware processing and add a pre-freeze script to the VM
B. In the virtual machines setting of the job, add a script in the scripts tab under "Run the following script before the job:"
C. Copy the script to the VM and schedule the script to run prior to the start of the backup job using the Windows Task Scheduler in the VM
D. Configure the script to run on the Veeam Backup & Replication server using the Windows Task Scheduler
正解:A
質問 5:
Select the correct description of a synthetic full backup.
A. A synthetic full backup combines a VIB file with one or more VBK files from a repository to generate a new VBK file
B. A synthetic full backup will generate a new VBK file by getting data from the hypervisor
C. A synthetic full backup combines a VBK file with one or more VIB files from a repository to generate a new VBK file
D. A synthetic full backup will update the existing VBK with data from the hypervisor and generate a new VRB file
正解:B