A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the following has the project manager identified?
A. Technological factors
B. Poor sample data
C. Scope creep
D. Language barriers
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Which of the following can a project manager infer from the following velocity chart?

A. The project is behind schedule.
B. The project Is ahead of schedule.
C. The project is at risk.
D. The project is on schedule.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
A project manager needs to pull data from a burndown chart. Which of the following should the project manager analyze to obtain this data in the most efficient way?
A. Cost variance
B. Number of issues registered
C. Number of people available
D. Remaining and completed tasks
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?
A. The team has members distributed around the world in different time zones.
B. The team is working in different rooms within the same building.
C. The team is based in the same office but has a large number of members.
D. The team is working remotely two days per week.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
A company purchases new software. The project manager needs to present the new software's features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?
A. Brainstorming
B. Status
C. Focus
D. Informative
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?
A. Monitoring the project team
B. Colocating the project team
C. Creating a handoff process
D. Creating a separate statement of work
正解:C
質問 7:
A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?
A. Contract obligations
B. Project scope
C. Quality plan
D. Work breakdown structure
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
A. Program manager
B. Scrum master
C. Lead architect
D. Project sponsor
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 9:
After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?
A. Rollback plan
B. Release plan
C. Contingency plan
D. Deployment plan
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
971 お客様のコメント
クリック」





Sakai -
PK0-005の問題集だけでで必要十分な知識を得ることができる。本当に受かった。サンキューPass4Test