During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.
Which of the following should have occurred to prevent this issue?
A. The project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.
B. During the planning phase, the project manager should have recognized the relationship between the vendor's and project team's tasks and adjusted the schedule for the project team to begin activities two months later.
C. During the project team's regular status meeting with the vendor, the vendor should have informed the project team that it required another two months, and to slow down.
D. During the project team's regular status meeting with the vendor, the project team should have informed the vendor that the team was ahead of schedule and to speed up their work.
正解:A
質問 2:
While working on a project, a self-organized team determines what will be accomplished during the next two weeks.
Which of the following describes what the team is doing?
A. Creating a WBS
B. Gathering continuous requirements
C. Sprint planning
D. Holding a Scrum meeting
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Management announces the PMO will assume all research and development efforts.
Which of the following BEST describes this scenario?
A. Process change
B. Relocation
C. Business merger
D. Outsourcing
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
During a meeting, a new member of the PMO says, "If this project fails, then the portfolio fails, and the program as a whole ultimately fails." Which of the following errors is the new PMO member making?
A. The new PMO member has not review the intra organizational strategy.
B. The new PMO member does not realize that although a project can fail, a program cannot, as it contains all projects in a company.
C. The new PMO member has not had an opportunity to review the company's project list.
D. The new PMO member has confused the relationship between portfolio and program.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?
A. Project backlog
B. Project management plan
C. Project status report
D. Project communication plan
正解:B