When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.
How does centralizing the risk management function help resolve the problem?
A. Establishes risk sources and ownership for trigger monitoring.
B. Allows monitoring the impact against the overall project risk exposure.
C. Creates a single repository for all project risk documents.
D. Enhance the process of identification of different Individual project risks.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?
A. Evaluate any new risks that are introduced due to the change in scope.
B. Update the risk management plan to reflect the scope change.
C. Update the risk register to identify, analyze, and plan a response for any new risk.
D. Reassess the identified risks that impact the project scope.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.
What should the project manager do next?
A. Update the communications management plan to avoid future issues
B. Identify secondary or residual risks for associated risk plans.
C. Monitor and control secondary and residual risks in the risk register.
D. Develop risk response plans for all identified risks.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.
What should the risk manager do to avoid the previous issues?
A. Create an issue log to share with the team.
B. Document the issues in the lessons learned.
C. Improve monitoring and controlling of activities.
D. Use the information for a risk workshop.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.
What type of risk is this?
A. Primary risk
B. Secondary risk
C. Normal risk
D. Residual risk
正解:B
解説: (Pass4Test メンバーにのみ表示されます)