A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.
Where should the project manager find this information?
A. Commercial risk databases
B. Organizational process assets (OPAs)
C. Industrial studies
D. Enterprise environmental factors (EEFs)
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.
How should the project manager address this concern with the health authorities?
A. Suspend the project as the secondary risk will negatively impact residents ' health which is not acceptable.
B. Assess and record associated secondary risks and proceed to treat them as any other risks.
C. Proceed with the project as normal since a minor number of residents will be effected negatively.
D. Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
The project manager wants to use an objective method to evaluate the key project risks and develop response plans.
What action should the risk manager propose?
A. Ask the team to perform an earned value analysis.
B. Review the lessons learned from other projects.
C. Ask the team to prepare a Monte Carlo analysis.
D. Ask the risk expert to perform a PESTLE evaluation.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
A financial institution is beginning a major digital-transformation project to enhance online-banking services.
The risk manager observes that team members from various departments are hesitant to participate actively in risk identification, potentially causing threats and opportunities to be overlooked.
What should the risk manager do?
A. Rely on historical risk data as an alternative way to predict potential project risks.
B. Personally identify risks to ensure accountability for effective risk management.
C. Hold collaborative interdepartmental meetings that enable the team to identify risks.
D. Encourage departments to focus on identifying threats to prevent potential impacts.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.
Which response should the risk manager recommend for these risk items?
A. Enhance
B. Exploit
C. Mitigate
D. Accept
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.
Which data will the risk manager require first?
A. Risk description risk response, and quantitative data
B. Project plan, risk priority, and tool availability
C. Project plan, risk complexity, and secondary risk
D. Risk description, risk probability, and risk impact
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a
50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.
What should the risk manager do next to find out the correct limit?
A. Find out the stakeholders' risk appetite
B. Review the agreed-upon risk tolerance
C. Perform a sensitivity analysis of the risk
D. Use industry standard risk thresholds
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime.
However, this action may lead to excessive additional cost.
What should the risk manager do?
A. Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project.
B. Manage the potential excessive additional cost as a new risk.
C. Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.
D. Document the concern over the potential excessive additional cost.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 9:
The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.
What should the project manager do?
A. Wait until the weather improves before sending the equipment.
B. Proceed with the planned risk response to move the equipment.
C. Request the shipment of the equipment to satisfy the client.
D. Ask the project sponsor to approve shipping the equipment.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
859 お客様のコメント





春川** -
Pass4Testの問題集を購入して合格するのはこれで三回目になります。