A new risk manager has been hired on a project and meets with the project director. The project director supplies the project's risk register and asks the risk manager for an analysis of its effectiveness.
What two actions should the risk manager do next? (Choose two.)
A. Check to ensure the risk meeting agenda and supporting documents are distributed.
B. Check for risk classification and that probability and impact are identified.
C. Check to ensure that the risks are gathered using Delphi technique.
D. Check to ensure that the risk is supported by a Monte Carlo simul-ation.
E. Check to ensure that risk origin, triggering event, and ownership is identified.
正解:B,E
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?
A. Coordinate a response with the risk owner.
B. Execute the security risks contingency plan.
C. Identify residual and secondary risks.
D. Get a report of customers affected by the risk.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.
Which type of analysis should the project manager use in this instance?
A. Cause and effect
B. Quantitative analysis
C. Specialized meeting
D. Check list analysis
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.
What should the risk manager do next to visually organize the risks?
A. Assign probability and impact
B. Develop an affinity diagram
C. Perform the analytical hierarchy process
D. Perform a SWOT analysis
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
The project's customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?
A. Update the assumptions/exclusions register
B. Hire more resources and crash the schedule
C. Perform a qualitative risk analysis for the project
D. Mitigate risks identified on the sensitivity analysis
正解:D
解説: (Pass4Test メンバーにのみ表示されます)