The project manager of a project that involves a system-wide computer update receives a report that some computers cannot be updated. Which of the following is a BEST practice?
A. Complete a project management change form without notifying the sponsor.
B. Contact the stakeholders in the project to determine the best course of action.
C. Perform an impact analysis and contact the project sponsor.
D. Document the change to the project without informing the stakeholders.
正解:C
質問 2:
A project has been going on for three weeks, and the project manager notices that Resource A is beginning to fall behind schedule. The project manager should FIRST schedule a meeting with:
A. The other team members to make up the schedule slippage.
B. The manager of Resource A for corrective action.
C. Resource A to confirm estimates.
D. The project stakeholders to communicate the delay.
正解:C
質問 3:
In which of the following areas would a transition plan be used?
A. When the project manager is added to the project and the project authority shifts to their responsibility
B. After the project receives approval and becomes an active project
C. At the end of the project to transfer maintenance responsibilities
D. As a project phase is completed and the project shifts to a new phase
正解:C
質問 4:
Which of the following techniques modifies the schedule based upon resource constraints?
A. Arrow Diagramming Method
B. Critical Path Method
C. Precedence Diagramming Method
D. Critical Chain Method
正解:D
質問 5:
An unexpected risk has been identified in a project. Which of the following actions should the project manager perform FIRST?
A. Perform a risk qualitative analysis
B. Add the risk to the risk register
C. Update the project probability / impact matrix
D. Submit a change request
正解:B
質問 6:
When forming a project team, there are a number of phases. When a project team is productive and effective this phase is known as which of the following?
A. Norming
B. Performing
C. Forming
D. Storming
正解:B