When would resource leveling be applied to a schedule model?
A. After critical activities have been removed from the critical path
B. Before constraints have been identified
C. Before it has been analyzed by the critical path method
D. After it has been analyzed by the critical path method
正解:D
質問 2:
What document should be reviewed by a project manager before finalizing the project closure?
A. Customer acceptance
B. User manual
C. Statement of work
D. Product report
正解:A
質問 3:
What tool and technique includes all costs incurred over the life of a product by investment in preventing nonconformance to requirements?
A. Cost of quality
B. Measure of design
C. Systematic analysis
D. Statistical control
正解:A
質問 4:
The product scope description is used to:
A. Gain stakeholders' support for the project.
B. Formally authorize the project.
C. Document the characteristics of the product.
D. Describe the project in great detail.
正解:C
質問 5:
In which of the team development stages are the teams interdependent and work through issues smoothly and effectively?
A. Norming
B. Performing
C. Forming
D. Storming
正解:B
質問 6:
Which process group can be performed outside the project's scope of control?
A. Planning
B. Closing
C. Monitoring and Control
D. Initiating
正解:D
質問 7:
What is the name of a graphic display of project team members and their reporting relationships?
A. Reporting flow diagram
B. Role dependencies chart
C. Project team structure diagram
D. Project organization chart
正解:D
質問 8:
In which of the following organizational structures does the project manager have full authority on a project?
A. Balanced matrix
B. Functional
C. Projectized
D. Strong matrix
正解:C
質問 9:
Which of the following is a schedule network analysis technique that takes limited resources into account?
A. Lead and lag adjustment
B. Network reserve analysis
C. Critical path method
D. Critical chain method
正解:D