Which of the following are components of the project management plan?
A. Scope management plan, scope baseline, risk management plan, and configuration managemet plan
B. Scope management plan, schedule baseline, milestone list, and assumption log
C. Scope management plan, cost estimates, duration estimates, and resource calenders
D. Scope management plan, issue log, risk register and project schedule network diagram
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
What is the definition of Direct and Manage Project Execution?
A. Developing and maintaining the plan
B. Execution of deliverables
C. Performing the activities included in the plan
D. Integrating all planned activities
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?
A. Move these user stories back to the product backlog for reprioritization.
B. Complete these user stories in the current sprint and extend the sprint length.
C. Remove these user stories as they are not important.
D. Advance these user stories to the top of the next sprint backlog.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
During which process group is the quality policy determined?
A. Executing
B. Planning
C. Controlling
D. Initiating
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
A. Seven
B. Six
C. One
D. Five
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
The project manager is finalizing a delivery solution and needs to choose a vendor to implement it. The project manager needs to use source selection criteria for evaluating vendor proposals. What should the project manager consider?
A. The vendor ' s adherence to internal policies.
B. The vendor ' s years of experience in the industry.
C. The vendor ' s capabilities and past performance.
D. The vendor ' s relationship with the project team.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
During a project team meeting, one of the team members suggested a product functionality that would immensely benefit the customer. The project manager documents the request for later analysis.
What is this an example of?
A. Managing the scope
B. Managing the cost benefit
C. Maintaining the product backlog
D. Monitoring the traceability matrix
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
Which type of estimating is used to improve the accuracy of an activity ' s duration?
A. Analogous
B. Parametric
C. What-if scenario analysis
D. Three-point
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 9:
What tool or technique is primarily used to plan risk responses ' ?
A. Risk management plan
B. Project risk document updates
C. Risk categorization
D. Strategies for overall project risk
正解:D
解説: (Pass4Test メンバーにのみ表示されます)