During which process would stakeholders provide formal acceptance of the completed project scope?
A. Control Scope
B. Verify Scope
C. Develop Schedule
D. Perform Quality Control
正解:B
質問 2:
Which Process Group and Knowledge Area include the Sequence Activities process?
A. Executing Process Group and Project Time Management
B. Executing Process Group and Project Cost Management
C. Planning Process Group and Project Cost Management
D. Planning Process Group and Project Time Management
正解:D
質問 3:
Match the process with its corresponding process group.

正解:

質問 4:
The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?
A. Plan Resource Management
B. Estimate Activity Resources
C. Acquire Resources
D. Estimate Costs
正解:B
質問 5:
Which procurement management process includes obtaining seller response, seller selection, and contract awarding?
A. Conduct Procurements
B. Perform Procurement
C. Manage Procurement
D. Plan Procurement
正解:A
質問 6:
Match the project manager's sphere of influence with the associated primary role.

正解:

質問 7:
For a stakeholder with low interest and high power, the project manager should:
A. Manage the stakeholder closely.
B. Monitor the stakeholder.
C. Keep the stakeholder informed.
D. Keep the stakeholder satisfied.
正解:D
質問 8:
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
A. Matrix
B. Affinity
C. Fishbone
D. Scatter
正解:A
質問 9:
Why is tailoring in a project necessary?
A. Each project is unique.
B. An artifact must be produced.
C. A tool or technique is required.
D. Requirements keep changing.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
Nakamata -
CAPM合格できました!試験だけをとってみても試験の設問がほぼ同じ問題がでたりと大助かりでした。
ありがとうございました。