What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
A. Use the progressed portion of the critical path of all the updates previous to the current update.
B. Use the forward-looking critical path of the most current updates.
C. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
D. Use the progressed portion of the critical path of the baseline schedule.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
A driving relationship is _____________________.
A. The link between a predecessor and the activity whose dates it controls.
B. The link between two related activities.
C. A critical relationship.
D. A finish-to-start relationship.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
A. 2.3% (1 : 43.501).
B. 8.6% (1 : 11.591)
C. 9.1% (1 : 11.000).
D. 3.9% (1 : 25.708)
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

A. 8 work days
B. 7 work days
C. 18 work days
D. 15 workdays
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Which of the following phases does NOT describe the commonly accepted construction life cycle?
A. Planning and design phase.
B. Installation phase.
C. Claims and disputes phase.
D. Turnover and start-up phase.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
What day would Activity C complete if the duration of Activity A was reduced by five days?
A. 40
B. 30
C. 35
D. 45
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
Which of the following project planning situations is the most frequent contributor to cost overruns?
A. lack of detailed planning for operational start-up
B. Inadequate definition of scope at the estimate (budget) stage
C. Insufficient planning for change management
D. Inappropriate definition of work breakdown structure
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
A good change management plan___________.
A. is provided to stakeholders after it is created
B. tracks minor decisions
C. involves only the project controls team
D. is detailed during the planning phase
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
Kouno -
問題集は受験者の方が短時間で効率良く試験対策できるように構成されていて、私を合格させることに成功しました。とにかくやさしく解説しています。だからわかりやすかったし、合格しました。