If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

A. 15 days.
B. 5 days.
C. 0 days.
D. 10 days.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?
A. 2003,8001.9001.9002,9005,10001
B. 5001,7001.8001,9001,9004,9005
C. 6001, 8001, 9001. 9002, 9004. 9005
D. 7001, 8001, 9001. 9003. 9004. 10002
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT
A. Look at each activity independently and don't follow specific logic paths when assigning activity durations.
B. Use gross building square footages. The pluses and minuses all average out.
C. Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.
D. Use the people responsible for performing the work as a resource to assign activity durations.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

A. 09-08-01.
B. 09-15-01.
C. 09-18-01.
D. 09-28-01.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Using the normal schedule, what is the early finish date and total float of Activity 10002?
A. 21 Dec 2023. and 4 days of total float
B. 24 Dec 2023. and 24 days of tree float
C. 24 Nov 2023. and 24 days of tree float
D. 17 Dec 2023. and 4 days of total float
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
Determine the correct formula and date for the late finish for Activity 6002.
A. LS of 6003 less 1 day equaling 09 Mar 2022
B. LS of 6003 plus 1 day equaling 09 Mar 2022
C. LS of 6003 plus 1 day equaling 09 Mar 2023
D. LS of 6003 less 1 day equaling 09 Mar 2023
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
How many workdays occur from the start of the Product Testing to the Product Available milestone?
A. 100
B. 70
C. 90
D. 60
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
Which of the following is NOT input data to the construction planning process?
A. Input from the owner
B. Input from the contractor
C. Bonding capacity of subcontractors
D. The contract
正解:C
解説: (Pass4Test メンバーにのみ表示されます)