The project team has completed the discovery and documentation of a process application for new hire onboarding. The project business sponsor and IT leadership have asked the BPM program manager to create a detailed project plan that identifies the estimated effort in hours and scheduled date of completion for each specific development task. In accordance with an agile BPM project, this request should be:
A. fulfilled as quickly as possible since the full scope of the project is frozen and it is necessary to schedule and budget for the necessary resources.
B. fulfilled by providing an iteration and release plan built with user story point estimate and a resource plan.
C. deferred until the software requirements specification document is complete.
D. delegated to the BPM Developer(s) since they have the most direct knowledge of the scope and nature of the development tasks.
正解:B
質問 2:
A program manager asks a developer to create a document describing the solution features that end user and system administrators needs to be aware or in order to deploy and use the process application. The developer tells the program manager that documentation is not a deliverable for any playback. The program manager responds by telling the developer that documentation required to enable later developers is a deliverable for which of the following playbacks?
A. Playback 2
B. Playback 3
C. Playback 1
D. Playback 0
正解:B
質問 3:
Key Performance Indicators (KPIs) are used by the process owner and stakeholders to:
A. determine the source of business data in the process.
B. measure the operations within a process.
C. reward participants for superior performance in the process.
D. notify stakeholders when a threshold is violated.
正解:B
質問 4:
The BPM Program Manager, Process Owner, and Lead Developer are collaborating to define the theme and assign user stories for the next iteration. The team is planning the 7th of 15 iterations in the Release Plan for Release One. The Program Manager displays a Team Velocity chart showing that the Development team has shown significant growth in story points accepted from iterations 1 to 4 and has been leveling off to roughly 200 story points in iterations 5 and 6.
Given there are 9 iterations remaining in the release plan, the Process Owner immediately recognizes there is room for roughly 1800 story points in the remaining time for Release One. However, the backlog contains 2400 story points marked as "high" priority and another 1200 story points marked as "medium" priority. The Process Owner asks to reduce the points assessed to the high priority user stories to bring the total points down to roughly 1800 so as to make them fit in the remaining time. The Program Manager agrees.
What is wrong with this scenario?
A. Process Owner forgot to include a risk factor of 1.4 that should be applied to 1800 resulting in roughly 2500 story points (1.4 x 1800 = 2520) remaining in the Release. No action should be taken.
B. Both "high" and "medium" priority stories should be included in the Release Plan meaning all user story points should be reduced by 50% to get all high/medium priority stories to fit in 1800 points remaining (2400+1200 = 3600 : 3600/2 = 1800).
C. This is a conversation for a Release Planning meeting and not during Iteration Planning.
D. Team Velocity is fixed and changing the method of estimating story points mid-way through a release will not increase the scope of work that can be completed.
正解:D
工藤** -
以前購入したよりもかなり安いです。結果はもちろん合格だよぉーん。これからもお世話になります。