Toward the end of the Iteration, the Product Owner raises a red flag stating there is an additional requirement that needs to be added to the current Iteration. The Agile Team could handle the requirement if they work late and over the next weekend. What should the Scrum Master do?
A. Talk to the Product Owner, compare the new work to existing backlog priorities, and negotiate a sustainable solution
B. Refuse the new requirement because it is too late to accept requirements at this point in the Iteration
C. Meet with the team and if they agree to work overtime, accept the work
D. Accept the work and extend the Iteration, informing other teams about the delay in delivery of other committed stories
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Which statement is true about optimizing batch sizes for newly-formed SAFe teams in a program?
A. Batch size is optimized immediately by looking at transaction and holding costs
B. Batch size optimization happens over time as teams figure out the balance between holding cost and transaction cost
C. Batch size is already optimized if there is continuous flow
D. Batch size is optimized when transaction and holding costs seldom change
正解:B
質問 3:
What is the appropriate Lean action to take once all of the expected value of an Epic has been delivered, even if all of the planned Features have not been completed?
A. Close the Epic
B. Continue building Features until the contract can be modified
C. Finish all of the Features since they were included in the contract
D. Initiate an early re-compete
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
What is the Manifesto for Agile Software Development?
A. A value system that only applies to software development
B. A shared set of values and principles intended to improve software development
C. A set of practices that originated from Scrum
D. A set of four values and twelve principles that help organizations implement systems thinking
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
What type of decision may significantly affect lead time for systems development?
A. Approved budget, required development tools, and dedicated team members
B. Using relative size estimating
C. Using firm fixed price contracts
D. Prioritizing the product backlog using WSJF
正解:C
解説: (Pass4Test メンバーにのみ表示されます)