An organization must accelerate a product to market. The program manager completes the preliminary program slaps and holds a kick-off meeting Project managers submit their preliminary schedules for review
What should the program manager do next?
A. Revise the project schedules to meet the program schedule and communicate to stakeholders
B. Assign resources lo the schedule and report the revised delivery date to the project managers
C. Work with the project managers to refine the project schedules and deliverables to align with the program milestones
D. Integrate the project schedules into the program schedule and report the revised delivery date to the project managers
正解:C
質問 2:
A program manager is appointed to manage a new program. The organization's leadership has specified a list of benefits (hat the program should deliver and has requested that the program manager determine when incremental benefits can be realized.
What should the program manager do first?
A. Develop the component project schedules
B. Develop the benefits sustainment plan
C. Develop the program management plan
D. Develop the program roadmap
正解:D
質問 3:
A two-year program is coming to an end Many of the initial governance board members have moved from their current posts or left the company Several new members have joined but have a shod association with the program, which changes the board's expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.
How should the program manager handle this situation?
A. Review the strategic plan and benefits management plan with the board
B. Review the final program outcome with the program sponsor
C. Prepare a program change request utilizing new board member input
D. Present the final program status, costs, and schedule reports
正解:A
質問 4:
Which two of the following are ADVANTAGES of underground conduit systems? (Select two options.)
A. Not adaptable for future facility placement or removal without disturbing the property
B. Route planning is not as critical as aerial or direct-burial
C. Economical over a long life
D. Provide additional physical cable protection
E. Require more installation time than aerial or direct-buried installations
正解:C,D
質問 5:
Which of the following terms is often used to describe two parallel paths that have identical conductive terminations to two separate grounding reference points?
A. Ground loop
B. Capacitive loop
C. Resistive loop
D. Inductive loop
E. Conductive loop
正解:A
質問 6:
Coupling with electrical circuits can create inductive interference to telecommunications facilities.
Which of the following can decrease the coupling effect?
A. Increase the earth resistance
B. Decrease the exposure length
C. Decrease the physical separation
D. Make sure that the single-phase components add in phase
正解:C
質問 7:
An RFQ usually provides more detail than RFP in selecting material such as:
A. make.
B. mounting option.
C. color.
D. delivery date.
正解:D
質問 8:
An organization requests that a junior project manager, with no previous experience or training in the industry take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.
How should the junior project manager respond to this request?
A. Accept the assignment, identify the skill gaps and request training
B. Accept the assignment as a challenge and an opportunity to acquire new skills and seek advice from a senior project manager
C. Reject the assignment because of fear of failure and resulting negative career impact
D. Reject the assignment, because of the ethical requirement not to accept work for which the project manager is not qualified
正解:A