最新なScrum PSM-II問題集(76題)、真実試験の問題を全部にカバー!

Pass4Testは斬新なScrum Professional Scrum Master PSM-II問題集を提供し、それをダウンロードしてから、PSM-II試験をいつ受けても100%に合格できる!一回に不合格すれば全額に返金!

  • 試験コード:PSM-II
  • 試験名称:Professional Scrum Master level II (PSM II)
  • 問題数:76 問題と回答
  • 最近更新時間:2025-05-06
  • PDF版 Demo
  • PC ソフト版 Demo
  • オンライン版 Demo
  • 価格:12900.00 5999.00  
質問 1:
During the Sprint Review the Product Owner introduces the functionality that is likely to be done over the next Sprints. The Chief Security Officer reminds everyone that through the envisioned functionality, sensitive personal user data will be stored. This might be the subject of external security audits. He reminds everyone of important non-functional requirements with regards to security. These were not applicable and not considered previously What are two effective ways the Scrum Team can manage these high-security concerns?
(choose the best two answers)
A. They are added to the Product Backlog and addressed throughout the next Sprints, combined with creating the business functionality in those Sprints, no matter how small that business functionality.
B. During the Sprint Retrospective, the Scrum Team assesses how to add these expectations to the Definition of Done so every future Increment will live up to these requirements. If needed they can work with external specialists to better understand the requirements
C. They should be managed by a separate specialist team in a parallel Sprint, so they can be specifically resolved through an improved application design without hindering functional development.
D. They are discussed, determined, and documented in parallel Sprints to not disturb the actual feature development Once analyzed, they should be applied to the work already done before further feature development can continue.
E. The impact of these security concerns on past and future work needs to be determined before new Sprints can start. A list of security-related Product Backlog items needs to be passed on to the Product Owner before starting the next Sprint
正解:A,B
解説: (Pass4Test メンバーにのみ表示されます)

質問 2:
Which two options describe how project budgeting and financial forecasting work in Scrum?
(choose the best two answers)
A. The only funding is for the run cost (time and materials) of the Scrum Teams, so no budgeting process is needed_
B. It is ideally revisited as frequently as each Sprint to ensure value is being delivered for the investment spent.
C. Scrum does not align with traditional accounting practices. The financial department needs to be given a fixed cost per Sprint per team.
D. Several Sprints may be funded as a single release, with the result of each Sprint being releasable product
正解:B,D
解説: (Pass4Test メンバーにのみ表示されます)

質問 3:
You are a Scrum Master employed by the IT department. The IT manager considers adopting Scrum tor a new project He wonders however, what the value is in having all team members attend this meeting called "Daily Scrum" every day. The organization already has its employees attending so many mandatory meetings.
What are two outcomes of the Daily Scrum you inform him about, to express the importance of the Daily Scrum?
(choose the best two answers)
A. During the Daily Scrum, the Developers need to update the Scrum board with their current status and progress, at a task level. This is crucial to ensure that the IT manager can go up to the room at any time and view the team's actual progress.
B. During the Daily Scrum the Developers will bring up problems that are hindering their progress, and tor which they nave no means to resolve, this provides an opportunity to resolve those impediments.
C. Through the snort, daily alignment of the Daily Scrum the Developers build and improve a shared understanding of the most important work to be undertaken in the next 24 hours, to achieve the best possible progress toward the Sprint Goal. This daily opportunity to inspect and adapt Will enable the Developers to tackle any unforeseen circumstances that might otherwise disrupt the team's progress.
D. The Daily Scrum serves tor the Developers to report to you, as a Scrum Master, all updates on the tasks to the Sprint, as registered in the Sprint Backlog. You can then use the team's updates to plan their work tor the next day, making sure that every team member is assigned the right tasks.
E. The Developers will produce a status report indicating what each individual has done the past working day, and now much time that has taken. The accumulated reports will support discussing how the Sprint went at the Sprint Review meeting. It will provide detailed insights into the accuracy of estimates versus actual time spent, which can be used to create better estimates at the subsequent Sprint Planning meeting.
正解:B,C
解説: (Pass4Test メンバーにのみ表示されます)

質問 4:
True or False: When multiple Scrum Teams work on the same product, they should employ a "Definition of Ready" to maximize their velocity. A "Definitlon of Ready" ensures that Sprint Planning can end within its timebox. This has a positive effect on the team's velocity, as the team will have more time for productive work.
A. False
B. True
正解:A
解説: (Pass4Test メンバーにのみ表示されます)

質問 5:
You are a Scrum Master and one of the Developers approaches you and says: Every Sprint we are not completing regression testing for all of the selected Product Backlog items in the Sprint, but regression testing is part of the Definition of Done. We have discussed with the Product Owner and during the Sprint we decided to change the Definition of Done to remove regression testing. Which two actions are appropriate in this situation?
(choose the best two answers)
A. Agree with altering the Definition of Done, if both the Developers and Product Owner agree.
B. Ask the Developers and the Product Owner what problem they are going to solve by altering the Definition of Done during the Sprint to remove regression testing. Will this raise transparency or improve quality?
C. Disagree with the decision and tell them that having a stringent Definition of Done is important for the quality of the product, and they need to follow it.
D. Ask the Developers and the Product Owner if removing regression testing from the Definition of Done allows the team to produce useful and valuable Increments at the end of every Sprint?
正解:B,D
解説: (Pass4Test メンバーにのみ表示されます)

質問 6:
In the Daily Scrum, the Product Owner applauds every Developer who moves a Sprint Backlog item to completion. The Product Owner wants to encourage the Developers to make progress visible on the burn-down chart. Select the two best options for the Scrum Master to take.
(choose the best two answers)
A. Tell the Product Owner your concerns about how his behavior may impact the Developers, and ask him to stop attending the Daily Scrum for some time.
B. Coach the Scrum Team about the purpose of the Daily Scrum.
C. Take the opportunity to create more energy and team spirit and encourage everyone to participate in the applause.
D. Nothing. The Scrum Master does not attend the Daily Scrum.
正解:A,B
解説: (Pass4Test メンバーにのみ表示されます)

質問 7:
Marian is a product Owner working on a Scrum Team on a new release for her product. Based on the average velocity of the previous release Marian estimated the project to take seven Sprints. Average velocity In the previous release was thirteen completed units of work per Sprint Development is three Sprints underway, with tour more Sprints to go until the release.
Product Backlog has been stable.
Over the first three Sprints, the Developers report their average velocity is nine, while not having fully tested all the delivered functionality. The Developers estimate that the unfinished testing would have required of a Sprints time. The Developers believe that the required velocity of thirteen is within their reach. What is the most effective way to recover?
(choose the best answer)
A. In the next Sprints, the Developers keep making sure that all of the selected scope per Sprint is as done as possible, at least at the past level of 90%. In every Sprint the undone work of the previous Sprint is estimated and added to the Sprint Backlog. It comes on top of the expected forecast of 13 units, so it does not mess up progress on the product Backlog.
B. Transparency needs to be restored by addng the undone work to the Product Backlog. The Developers must figure out a way to deliver in the upcoming Sprintsa velocity of not only
13 units of new work, but also two additional points to catch up undone work. It is the Scrum Master's duty to assess whether such repair is possible. If not, the Scrum Master initiates a restart with a more reliable team Or cancels the project. The Scrum Master will have to inform Product Owner and the stakeholders.
C. The Developers inform Marian that the progress she has perceived to date is not correct The Increment is not releasable. They give Marian their estimate of the effort it would take to get the past work done, and suggest doing that work first before proceeding with new features. The Developers also re-estimate the effort to complete the remaining backlog, including all testing. In the end, it is Marian's call to continue the project or to cancel.
D. The Developers set the open work aside to be performed in one or more release Sprints. They remind Marian to find funding for enough Release Sprints in which this remaining work can be done. up to one release Sprint per three development Sprints may be required, It is Marian's responsibility to inform users and stakeholders Of the impact on the release date.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)

質問 8:
What does the Scrum Team commit to each Sprint?
(choose the best three answers)
A. Working towards the Sprint Goal.
B. Getting all the forecast work in the Sprint Plan done
C. Seeking stakeholder feedback.
D. Upholding transparency
E. Having the Product Owner available to the Developers on a daily basis
F. Increasing velocity
正解:A,C,D
解説: (Pass4Test メンバーにのみ表示されます)

一年間無料で問題集をアップデートするサービスを提供します。

弊社の商品をご購入になったことがあるお客様に一年間の無料更新サービスを提供いたします。弊社は毎日問題集が更新されたかどうかを確認しますから、もし更新されたら、弊社は直ちに最新版のPSM-II問題集をお客様のメールアドレスに送信いたします。ですから、試験に関連する情報が変わったら、あなたがすぐに知ることができます。弊社はお客様がいつでも最新版のScrum PSM-II学習教材を持っていることを保証します。

弊社は無料でProfessional Scrum Master試験のDEMOを提供します。

Pass4Testの試験問題集はPDF版とソフト版があります。PDF版のPSM-II問題集は印刷されることができ、ソフト版のPSM-II問題集はどのパソコンでも使われることもできます。両方の問題集のデモを無料で提供し、ご購入の前に問題集をよく理解することができます。

簡単で便利な購入方法ご購入を完了するためにわずか2つのステップが必要です。弊社は最速のスピードでお客様のメールボックスに製品をお送りします。あなたはただ電子メールの添付ファイルをダウンロードする必要があります。

領収書について:社名入りの領収書が必要な場合には、メールで社名に記入して頂き送信してください。弊社はPDF版の領収書を提供いたします。

Scrum PSM-II 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Developing and Delivering Products Professionally
  • Empiricism, Scrum Values, Roles, Events, Artifacts
トピック 2
  • Product Backlog Management, Stakeholders & Customers
  • Managing Products with Agility
トピック 3
  • Evolving the Agile Organization
  • Understanding and Applying the Scrum Framework
トピック 4
  • Developing People and Teams
  • Managing Technical Risk
  • Organizational Design & Culture
トピック 5
  • Self-Organizing Teams, Facilitation, Leadership Styles, Coaching and Mentoring

参照:https://www.scrum.org/professional-scrum-master-ii-certification

弊社のProfessional Scrum Master問題集を利用すれば必ず試験に合格できます。

Pass4TestのScrum PSM-II問題集はIT認定試験に関連する豊富な経験を持っているIT専門家によって研究された最新バージョンの試験参考書です。Scrum PSM-II問題集は最新のScrum PSM-II試験内容を含んでいてヒット率がとても高いです。Pass4TestのScrum PSM-II問題集を真剣に勉強する限り、簡単に試験に合格することができます。弊社の問題集は100%の合格率を持っています。これは数え切れない受験者の皆さんに証明されたことです。100%一発合格!失敗一回なら、全額返金を約束します!

弊社のPSM-II問題集のメリット

Pass4Testの人気IT認定試験問題集は的中率が高くて、100%試験に合格できるように作成されたものです。Pass4Testの問題集はIT専門家が長年の経験を活かして最新のシラバスに従って研究し出した学習教材です。弊社のPSM-II問題集は100%の正確率を持っています。弊社のPSM-II問題集は多肢選択問題、単一選択問題、ドラッグ とドロップ問題及び穴埋め問題のいくつかの種類を提供しております。

Pass4Testは効率が良い受験法を教えてさしあげます。弊社のPSM-II問題集は精確に実際試験の範囲を絞ります。弊社のPSM-II問題集を利用すると、試験の準備をするときに時間をたくさん節約することができます。弊社の問題集によって、あなたは試験に関連する専門知識をよく習得し、自分の能力を高めることができます。それだけでなく、弊社のPSM-II問題集はあなたがPSM-II認定試験に一発合格できることを保証いたします。

行き届いたサービス、お客様の立場からの思いやり、高品質の学習教材を提供するのは弊社の目標です。 お客様がご購入の前に、無料で弊社のPSM-II試験「Professional Scrum Master level II (PSM II)」のサンプルをダウンロードして試用することができます。PDF版とソフト版の両方がありますから、あなたに最大の便利を捧げます。それに、PSM-II試験問題は最新の試験情報に基づいて定期的にアップデートされています。

1379 お客様のコメント最新のコメント

Honjou - 

ソフト版とPDF版のPSM-II試験復習資料が勉強と、最終仕上げに役立ちました。見事で合格できました。
とても助かりました。ありがとうございました!

Otani - 

Pass4Testのおかげで無事合格だぁ!!PSM-IIこの問題集はとてもわかりやすいので、しっかりとした理解に導いてくれるScrumのPSM-II問題集が合格への最短ルートです。

Ittougi - 

PSM-IIに合格しました。また次回もここにお世話になりたいと思います。PSM-IIの知識がない未経験者、学生の方でもついてこれるぐらいに初歩からじっくり学べるのは良い点

すず** - 

Scrum会社のサービスもいい、PSM-II学習教材もいいです。だから、私はPSM-II試験に合格しました。

源氏** - 

すごいね。Pass4Testさんまたお世話になりたいとおもいます。本当に助かりました。誠に有難うございます

Kaizu - 

試験(PSM-II)を受験をして、合格できました。
出題についてはかなり出題されていたので、楽勝です。

河*瞳 - 

最新試験に対応してますし、教科書と過去問題も、このPSM-II問題集一つに集約していて素晴らしいですね。ありがとうございます。

知念** - 

よかったです。ありがとうございました。本格的なPSM-II問題も掲載されてる

Mizaki - 

PSM-II問題集の問題はなぜか本番試験にほぼ出てて、高いスコアで合格するには十分ですね。

田中** - 

たくさん問題を解いておきたい方にはおすすめできますね。出題範囲を100%カバーしている。Pass4TestのPSM-IIは最強。友達にも勧めました。

Hagiwara - 

今日はPSM-II試験に合格しました。試験する前に、緊張しました。でも、試験内容を見ると、多くの問題がPSM-II問題集に出ることがあります。

高松** - 

非常に読みやすく、ストレスなく勉強を続けられました
分かりやすかったです。

Naitou - 

PSM-II主要論点を網羅することはさすがに無理でしょうが、試験対策としてはこれだけで十分でしょう。Pass4Testあざっす

Niiyama - 

問題も解説も良質なので、たくさん問題を解いておきたい方にはおすすめできますね。
しかも試験の問題にも入ていて、高得点で受かりました。

Kuroki - 

試験に合格するために必須の基本知識がこのPSM-II問題集一つでで短時間に修得できると思います。スムーズにかけたし、合格することもできました。

Maeda - 

私はもう一度う買いたいです!PSM-IIの問題集滅多にいいもんないけどこれだけはいいと思う。

矢野** - 

PSM-II主要論点を網羅することはさすがに無理でしょうが、試験対策としてはこれだけで十分でしょう。Pass4Testあざっす

夏帆 - 

PSM-IIの問題集だけでで必要十分な知識を得ることができる。本当に受かった。サンキューPass4Test

河西** - 

Pass4Testの問題集はPSM-II試験過去問を徹底的に分析。「優秀答案」のすべてが、予備試験A評価の答案合格者の「思考過程」がわかると、答案の組み立て方もわかる。

Kaneko - 

PSM-II試験めっちゃ余裕でね!!すべてはPass4Testさんから提供された素晴らしい問題集のおかげです!しかも高得点。次はPSM-Iに挑戦したいと思います!

北*香 - 

PSM-II知識も経験も無しにいきなりこの試験から受けるという方はいないでしょう。きっちりと情報がまとまっているし

Kiriake - 

PSM-II問題集は図表が多く、説明も丁寧で読み込むことにより合格に必要な知識を得ることができます。

远野** - 

PSM-II初学者のわしでも比較的習得しやすいですね。だれよりもラクにPSM-II合格を勝ちとったぜ。

Ikeuchi - 

Pass4Testさんの問題集を購入するのはこれで四回目になりました。今回も無事合格です。

メッセージを送る

あなたのメールアドレスは公開されません。必要な部分に * が付きます。

Pass4Test問題集を選ぶ理由は何でしょうか?

品質保証

Pass4Testは試験内容に応じて作り上げられて、正確に試験の内容を捉え、最新の97%のカバー率の問題集を提供することができます。

一年間の無料アップデート

Pass4Testは一年間で無料更新サービスを提供することができ、認定試験の合格に大変役に立ちます。もし試験内容が変われば、早速お客様にお知らせします。そして、もし更新版がれば、お客様にお送りいたします。

全額返金

お客様に試験資料を提供してあげ、勉強時間は短くても、合格できることを保証いたします。不合格になる場合は、全額返金することを保証いたします。

ご購入の前の試用

Pass4Testは無料でサンプルを提供することができます。無料サンプルのご利用によってで、もっと自信を持って認定試験に合格することができます。