A photovoltaic (PV) system was installed after commissioning (Cx) was completed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification?
A. The building's electrical engineer should commission the installation and share the results with the project owner
B. The PV system installer should commission their own installations and share the results with the project owner
C. No action is necessary as the PV system is not required to be commissioned
D. The Cx agent for the project must return and conduct or oversee the commissioning of the PV system
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
When developing the overall energy strategy of the project, which credit should the client consider to work synergistically with the Energy and Atmosphere Credit, Enhanced Commissioning, on an ongoing basis?
A. Green Power and Carbon Offsets
B. Renewable Energy Production
C. Advanced Energy Metering
D. Enhanced Refrigerant Management
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
A 1,500 ft2 (139 m2) mobile home is built in the downtown area of a major city. 90% of the project's gross floor will be completed by the time of occupancy. LEED certification is being sought. Which rating system would be the most appropriate one to use?
A. No rating system
B. LEED for Homes
C. LEED Interior Design and Construction
D. LEED Building Design and Construction
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
The Commissioning Authority (CxA) must report results, findings and recommendations directly to the
A. project manager
B. architect
C. contractor
D. owner
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Which standard reference can be used to find minimum ventilation rates?
A. SCAQMD Rule 1168
B. ASHRAE 62.1-2010
C. ASHRAE 55-2010
D. ASHRAE 90.1-2010
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
In a goal-setting workshop, a project team identifies that teleworking could reduce building area and therefore the required plug loads. What is a requirement for the documentation of the energy-related systems of the Integrative Process worksheet?
A. Providing explanations of at least two plug load reduction strategies
B. Providing a narrative of one plug load reduction
C. Providing detailed comparative energy model before completing schematic design to evaluate energy load reduction strategies
D. Providing calculations of only the plug load reduction
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
Design is underway for a new tenant suite with 4,000 ft2 (371.6 m2) of net occupiable area. The project build-out will include all new HVAC systems. Operable windows are installed as follows:
A total 75 ft2 (7.0 m2) located within 15 ft. (4.6 m) of all spaces
. A total 50 ft2 (4.6 m2) located within 25 ft. (7.6 m) of all spaces
Which design and documentation strategies must be used to demonstrate compliance with Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?
A. Install 25 ft2 (2.3 m2) of new operable windows within 25 ft. (7.6 m) of all spaces and tabulate the total area of operable windows to indicate compliance
B. Tabulate the total area of operable windows to indicate compliance. No mechanical outside air systems required for space HVAC design
C. Provide MERV 13 (F7) filters on the new HVAC system air handling units. No mechanical outside air systems required for space HVAC design
D. Provide new mechanical outside air systems in compliance with ASHRAE 62.1-2010 and document compliance by tabulating rates in compliance with the standard
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
Takagi -
LEED-AP-ID-C試験に合格しました!LEED-AP-ID-C試験資料は本当に有効的です。友達にお勧めするつもりです。