XYZ Ltd is producing an engine which consists of many components. The procurement manager wants to find cost reduction opportunities and minimise part varieties. Which of the following may help her to achieve these objectives?
1. Value analysis
2. Segment analysis
3. Variety reduction
4. Standardisation
A. 1 and 3 only
B. 1 and 4 only
C. 3 and 4 only
D. 2 and 3 only
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
A procurement manager includes provision on recovery from natural disaster into a through-life specification.
Some suppliers suppose that provision is unnecessary. Is procurement manager's action justified?
A. No, because this provision will incur unnecessary cost to supplier
B. No, because with current technology, natural disaster can't disrupt supply chain.
C. Yes, because natural disaster may cause risks in organisation's supply chain
D. Yes, because the regulations require contract to have recovery provision
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
A buyer in Housing Authority is considering using performance specification in upcoming social housing project. What should buyer be aware when using this type of specification?
A. In performance specification, specific brands and preferred suppliers must be appointed to avoid the competition
B. Using performance specification means that the buyer will bear all the risks regarding the fitness for purpose of the facility.
C. The buyer must be able to clearly define the performance metrics to ensure that the of-fered solution will achieve the desired outcome
D. The buyer must be able to define the materials to be used, the execution and installation methods required and the specific design of the building
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Which of the following problems may be identified as open-ended problems? Select TWO that apply:
A. Logistics costs incur a large portion in wholesale prices
B. The suppliers don't comply with the company's policy on underage labour.
C. Shortage of key medicines in healthcare industry
D. A cyber attack takes down whole company's IT system
E. Engine failures cause flight cancellations.
正解:A,B
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
GE has developed TurboProp engine that is made from over 850 metal parts. These parts are sourced from many suppliers. Value of spend on these parts make up 73% of total spend. Any delay in receiving a part will cause a bottleneck around the production of the engine. Which of the following should be the best course of action of GE's CPO?
A. Drive down prices by using market competition
B. Reduce delivery cost
C. Increase production
D. Part standardisation
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
Abe -