A team finds a non-critical bug. They create a task on their Scrum board to solve that bug. If they decide to solve the bug right now, they will need to drop a task that is essential to the sprint goal.
What is the best action to take next?
A. Put the task on the product backlog for ordering by the Product Owner and fix the bug later
B. Pull the task into the sprint backlog to solve it immediately and track ii on the Scrum board
C. Put the task on the sprint backlog and address it only when there is room left in the sprint
D. Pull the task to the doing column and have the entire team swarm the problem like a roadblock
正解:A
質問 2:
A Scrum Team is supposed to deliver potentially snippable software at the end of each Sprint. During the last Sprint the Team did not deliver a potentially shippable increment.
The correct question to ask is: "What can we do to make sure we do better in the next Sprint?" Who is responsible for making sure this question asked?
A. The Scrum Master
B. The Development Team
C. The Project Manager
D. The Product Owner
正解:A
質問 3:
One of the responsibilities of the Scrum Master is to facilitate timely identification of all risks faced by the Scrum Team. As the Scrum Master for a team working on a banking application project, which of the following techniques would you suggest for comprehensive risk identification?
A. Risk Checklists.
B. Risk Appetite.
C. Probability Impact Grid.
D. Risk Meeting.
正解:C
質問 4:
You are the Scrum Master and you're coaching the Development Team on creating a Sprint Goal. The team doesn't understand why they need to create a Sprint Goal. What should you tell the Development Team?
A. The Development Team needs a Sprint Goal to create a communications plan of who does what and when.
B. The Development Team needs a Sprint Goal to communicate exactly who'll do what in the Sprint.
C. The Development Team needs a Sprint Goal so they'll see the value and importance of completing all of the user stories selected for the Sprint meet the definition of done.
D. The Development Team needs a Sprint Goal to create synergy among the Development Team members.
正解:C
質問 5:
Collaboration within a team is an important principle of Scrum. All of the following activities constitute collaboration EXCEPT:
A. The Scrum Team discusses the best approach to creating deliverables during a Sprint.
B. The Scrum Team interacts with the Product Owner to obtain clarification on User Stories.
C. The Scrum Team decides which User Stories are important and assigns which Sprint they should be worked on.
D. A Scrum Team member is facing difficulties in one of his tasks and another team member pitches in to help him.
正解:C