Scrum effectively limits the risk of unknowingly doing something wrong by
A. Having multiple checkpoints and a thorough review by senior management at those checkpoints
B. Having a detailed and extensive risk management plan
C. Using short iterations called Sprints
正解:C
質問 2:
During a Scrum of Scrums, each Scrum Team representative provides an update on which of the following:
A) What has my team been working on since the last meeting?
B) What will my team do until the next meeting?
C) How many story points has my team completed since the last meeting?
D) What is our team planning on doing that might affect other teams?
A. , C, and D
B. A, C, and D
C. A, , and D
D. A, , and
正解:D
質問 3:
The Product Owner on a project, on which you are the Scrum Master, has identified disaster situations, such as earthquakes and tsunamis, as potential risks to the underwater transnational communication sea link. The Stakeholders have suggested that steps to safeguard the foundations of the ocean infrastructure be taken at the earliest, and also have recommended that a contingency reserve be created, which could be used in case of disaster situations. This is an example of:
A. Risk Prioritization.
B. Risk Assessment.
C. Risk Mitigation.
D. Risk Avoidance.
正解:C
質問 4:
A team needs a new Scrum Master. The team has been experiencing some problems in creating a good flow of their work. The task board is not used as it should be Some of the team members find it difficult to speak to coworkers outside of their team although they are very open with each other. The team is very experienced in their job What is the most important characteristic for this new Scrum Master?
A. Being new to the organization and having a fresh look at things
B. Having experience in different projects and with new technologies
C. Having the ability to remove impediments to the team's progress
D. Being very assertive when communicating and making decisions
正解:A
質問 5:
One of the responsibilities of the Scrum Master is to facilitate timely identification of all risks faced by the Scrum Team. As the Scrum Master for a team working on a banking application project, which of the following techniques would you suggest for comprehensive risk identification?
A. Risk Checklists.
B. Risk Appetite.
C. Probability Impact Grid.
D. Risk Meeting.
正解:C