What data can be posted directly via the Plant Data Collection (PP-PDC) interface?
A. Goods receipts
B. Confirmations
C. Maintenance notifications
D. Goods issues
正解:B
質問 2:
Which of the following statements regarding ATP checks in SAP ECC that are triggered from customer orders is correct?
A. If the ATP check determines non-availability. It then checks in the next step whether it is possible to procure or produce in time.
B. The ATP quantity is the available quantity, which can be used to confirm incoming customer orders.
C. The ATP check does not take stocks and receipts into account. It checks consumption of planned independent requirements.
D. An ATP check creates fixed links between customer orders and their confirmed receipts.
正解:A
質問 3:
Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)
A. Confirming the operation
B. Posting the goods receipt for the production order
C. Reducing the order quantity
D. Setting the status technically complete (TECO)
E. Rescheduling the operation
正解:A,C,D
質問 4:
The final assembly of a finished product should only be triggered when a customer order arrives.
Which planning strategy for the finished product do you use?
A. Planning without final assembly (strategy 50)
B. Planning with final assembly (strategy 40)
C. Planning with make-to-stock (strategy 10)
D. Planning at the assembly level (strategy 70)
正解:D
質問 5:
Which functions can be triggered before releasing a production order? (Choose three)
A. Selection of a BOM
B. Scheduling
C. Selection of a routing
D. Confirmation
E. Stock determination
正解:A,B,C
質問 6:
Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master.
How is the resulting firming interval specified in this scenario?
A. It is predefined in Customizing.
B. By the planning time fence from the material master.
C. By the manual firming date.
D. By the firming mechanism that spans further into the future.
正解:D
質問 7:
Which of the following elements can be used in a process order? (Choose three)
A. Relationships
B. Parallel sequences
C. Process instructions
D. Phases
E. Suboperations
正解:A,C,D
質問 8:
What option for selecting a routing exists when creating a production order?
A. Manual selection based on the list of routings maintained in the material master
B. Manual selection based on settings in the order type-dependent parameters
C. Automatic selection of a reference operation set
D. Automatic selection based on settings in the production scheduling profile
正解:B