What are characteristics of repetitive manufacturing? (Choose three)
A. Automatic line loading based on capacity limits across all production lines
B. Shop fabrication
C. Continuous material consumption, production flow and output
D. Production without using production orders and without status management
E. Period-based planning of the quantities to be produced
正解:C,D,E
質問 2:
Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?
A. Lead time scheduling cannot take place.
B. Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
C. Requirements planning creates an appropriate exception message in basic dates scheduling.
D. Dependent requirements request the components from the bill of materials at wrong times when using basic dates scheduling.
正解:D
質問 3:
What sequence do you follow in master data maintenance to define the production of a material?
A. Create routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or routing
B. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing
C. Create work centers -> Create routing -> Create BOM -> Carry out component assignment in work center
D. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
正解:B
質問 4:
Which objects can affect the calculation of capacity requirements for an operation? (Choose three)
A. Standard values (routing)
B. Operation control key (routing)
C. Transport time (routing)
D. Formulas (work center)
E. In-house production time (material master)
正解:A,B,D
質問 5:
You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence.
What do you have to consider in this scenario?
A. Planned orders are created within the planning time fence and automatically firmed by requirements planning.
B. Planned orders that are created by requirements planning are shifted to the end of the planning time fence.
C. Requirements planning considers only changes that are relevant for scheduling within the planning time fence.
D. The MRP controller cannot create planned orders within the planning time fence.
正解:B
質問 6:
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)
A. Approved master recipes
B. Resource selection
C. Availability check
D. Electronic batch record
E. Digital signature
正解:A,D,E
質問 7:
Which Customizing element controls the determination of planned costs in production orders?
A. Settlement profile
B. Calculation procedure
C. Accounting type
D. Costing variant
正解:D
質問 8:
Which repetitive manufacturing options can you use to carry out line loading in the SAP ECC system and thus generate run schedule quantities (RSQ) from normal planned orders? (Choose three)
A. Automatic selection of the production version in material requirements planning (MRP) using selection methods setting
B. A suitable repetitive manufacturing profile that contains an option for automatic line selection
C. Manual assignment of planned production quantities in a planning table
D. Automatic selection of the production version by applying quota arrangement records in material requirements planning (MRP)
E. A planning algorithm from capacity planning
正解:A,C,D