A project manager is performing a specific process and has..........is being referred to?
A project manager is performing a specific process and has a list of accepted deliverables One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables Which process is being referred to?
A. Control Scope
B. Validate Quality
C. Control Quality
D. Validate Scope
正解:D
質問 2:
What process is performed periodically throughout the project as needed?
A. Plan Risk Management
B. Plan Communications Management
C. Plan Resource Management
D. Plan Cost Management
正解:C
質問 3:
Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
A. Risk, resource, and communications management plans
B. Communications, schedule, and cost management plans
C. Scope, quality, and resource management plans
D. Procurement, integration, and risk management plans
正解:A
質問 4:
An input to the Plan Cost Management process is:
A. The risk register.
B. Resource calendars,
C. Cost estimates.
D. The project charter,
正解:D
質問 5:
Stakeholder satisfaction should be managed as a key project:
A. Objective
B. Benefit
C. Process
D. Initiative
正解:A
質問 6:
An executive sponsor wants to be briefed on how the product will change over time. Which document should the business analyst use to prepare their presentation?
A. Product roadmap
B. Project charter
C. Project management plan
D. Product requirements
正解:A
質問 7:
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
A. Stakeholder participation.
B. Enterprise environmental factors.
C. Expert judgment
D. Communication models.
正解:C
質問 8:
Projects programs subsidiary portfolios.... objectives refer to?
Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?
A. Portfolio Management
B. Program Management
C. Operations Management
D. Project Management
正解:A
質問 9:
A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?
A. Identify the path through the schedule with leveled resources and the shortest duration.
B. Identify the longest activity path in the schedule with the shortest possible duration.
C. Identify the crashed project schedule to find the shortest duration to complete the project.
D. Identify the tasks with float duration, which do not impact the duration of the project.
正解:B