After you completed the Explore Phase Quality Gate you notice that the Fit to Standard workshops have been carried out without the input of the finance experts of the Australian office of the customer. The Australian office is scheduled to go live in a later implementation phase. What should you do? Note: There are 2 correct answers to this question.
A. Proceed with the as-is plan because the Australian office of the customer is scheduled for a later implementation phase.
B. Get approval from Australian key users on any of the configuration items that cannot be changed after system provisioning.
C. Review the scope items to ensure their functionality is available and appropriate for use by Australian users.
D. Put the project on hold and run all required Fit to Standard workshops with Australian users.
正解:B,C
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
What accelerator can help you document the configuration definition in the Explore phase?
A. Backlog template
B. Data definition template
C. Change request template
D. Test plan template
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
What are some benefits for customers of using the SAP Activate methodology? Note: There are 3 correct answers to this question.
A. It relies on a traditional Waterfall approach for all project implementations, thus providing predictable outcomes.
B. It is designed to streamline the implementation process by reducing resource requirements from the customers and partners.
C. It offers customers accelerators to help run their project as efficiently as possible.
D. It guides customers through the entire SAP S/4HANA Cloud lifecycle and provides quick value realization.
E. It contains time-phased instructions to help execute tasks throughout the implementation journey.
正解:C,D,E
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Which organizational change management activity is usually performed in which SAP Activate phase? Note:
There are 2 correct answers to this question.
A. The change plan is usually developed in the explore phase.
B. The business readiness assessment is usually conducted in the discover phase.
C. The change assessment is usually conducted in the prepare phase.
D. The user adoption analysis is usually conducted in the run phase.
正解:C,D
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Why does SAP recommend to perform regression testing during the upgrade window for SAP S/4HANA Cloud Public Edition?
A. To verify existing functionality still works correctly after the upgrade
B. To confirm that the database schema changes have been implemented successfully
C. To validate that all user permissions have been properly migrated to the new version
D. To ensure that new features of the upgrade are working as specified in the requirements
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
How is SAP's organizational change management framework connected with the SAP Activate methodology?
Note: There are 2 correct answers to this question.
A. Each change management dimension is assigned to a specific SAP Activate phase.
B. Some change management activities are executed in more than one SAP Activate phase.
C. The SAP Activate phases build the dimensions of the organizational change management framework.
D. The start of each change management activity is assigned to one specific SAP Activate phase.
正解:B,D
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
A mid-market customer wants to add a small sales agency (15 employees) office to their existing SAP S
/4HANA Cloud Public Edition system. The sales agency is located in a country that was localized two years ago. The sales agency plans to use SAP Best Practice scope items and the org structure as is. The original Digital Discovery Assessment (DDA) did not identify any integration or extensibility requirements. Using the
"Simple" configuration transport mode for the deployment of the sales agency, how should the project manager proceed?
A. Plan the last active sprint for any previous deployment wave to be completed so that all opentransports are released before turning on Simple Transport Mode via the Custom Logic App
B. Plan to have multiple deployment waves open at the same time using both Simple and Flexible transport modes via the Export Software Collection App
C. Plan the last active sprint for any previous deployment wave to be completed so that all open transports are released before turning on Simple Transport Mode via the Extensibility Settings App
D. Plan the last active sprint for any previous deployment wave to be completed and fully tested before turning on Simple Transport Mode via the Export Software Collection App
正解:C
解説: (Pass4Test メンバーにのみ表示されます)