A project manager is justifying a required change with the associated impact on the project.
Which of the following is the NEXT step?
A. Auditing
B. Implementation
C. Validation
D. Approval
正解:D
質問 2:
A senior manager asks a project manager for an estimated budget on a new project.
Which of the following is the BEST step for the project manager to take?
A. Ask a SME for an opinion and propose an estimate.
B. Use the budget from a similar project to generate estimates.
C. Gather the team to immediately generate estimates.
D. Tell the senior manager the estimation is not available yet.
正解:B
質問 3:
The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?
A. Cost variance report
B. Burn rate
C. Cost baseline
D. Total project cost
正解:C
質問 4:
A vendor is unable to deliver an order by the specified date.
Which of the following should be the project manager's NEXT steps? (Choose two.)
A. The project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline.
B. The project manager should adjust the schedule in the documentation and, if necessary, take steps to rush other areas of the schedule so the project will not encounter delays.
C. The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.
D. The project manager should notify the project sponsor to update the schedule in the documentation because the project could potentially encounter delays.
E. The project manager should update the procurement plan and action items to reflect the possible delay in the project timeline.
正解:A,C
質問 5:
After identifying all known tasks, the project manager has started to sequence and set durations.
Which of the following describes how the project manager should BEST determine the initial sequence and durations?
A. Use data based on past knowledge.
B. Collaborate with other project managers.
C. Use milestones identified in the project charter.
D. Hold a full team workshop to review the complete WBS.
正解:C
質問 6:
Which of the following are characteristics of a project? (Choose two.)
A. Ongoing
B. Consisting of milestones
C. Temporary
D. Restricting the budget
E. Start and finish
F. Achieving a goal
正解:C,E
質問 7:
One deliverable failed during testing, and this has already happened several times.
Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?
A. Gantt chart
B. Scatter diagram
C. Fishbone diagram
D. Run chart
正解:C
質問 8:
A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change.
Which of the following is the MOST likely reason?
A. Established communication plan
B. Scope creep
C. Resource constraints
D. Iterative approach
正解:B