The PMO is responsible for: (Choose two.)
A. approving funding, developing the project schedule, and gathering high-level requirements.
B. outlining consequences of non-performance and coordinating between disparate projects.
C. managing the project plan, scope, risk, and budget.
D. setting standards and practices for the organization and providing governance.
E. contributing expertise, deliverables, and estimates of costs.
正解:B,D
質問 2:
Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.
Which of the following techniques is the project manager using?
A. Compromising
B. Smoothing
C. Accepting
D. Withdrawing
正解:D
質問 3:
Which of the following is a schedule that illustrates the duration of an activity?
A. Gantt chart
B. Process diagram
C. Ishikawa diagram
D. Pareto chart
正解:A
質問 4:
Which of the following is a key aspect of the Agile project management methodology?
A. Daily standup meetings
B. Test-driven
C. Short project durations
D. Defined list of requirements
正解:A
質問 5:
A project manager is managing a transactional project. One of the key team members is having difficulties understanding the client requirements.
Which of the following actions would be BEST for the project manager to take?
A. Ask the client to provide additional language resources to the team.
B. Purchase a language translation program.
C. Hire a translator to help the key team member
D. Ask the client to provide requirements in the native language of the team.
正解:D
質問 6:
A project in the execution phase is over budget, and tasks on the critical path are on schedule.
Which of the following should the project manager do NEXT?
A. Evaluate the impact to the baseline.
B. Revise the project charter.
C. Issue a change request.
D. Update the project management plan.
正解:A
質問 7:
Which of the following is a definition of an RFP?
A. A document sent to potential vendors to solicit information that excludes pricing information for a project.
B. A document sent to potential vendors to solicit a bid for a project.
C. A document sent to potential vendors to request a commitment for a project.
D. A document sent to potential vendors to request information for skills and experience for a project.
正解:B
質問 8:
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:
A. compromising.
B. forcing.
C. smoothing.
D. avoiding.
正解:B