Who should be defined as the owner of a risk?
A. The person responsible for defining the probability of the risk.
B. The person best placed to take the necessary counter-measures to the risk
C. The person who documented the risk in the risk register
D. The person who identified the risk in the initial requirements analysis.
正解:B
質問 2:
Which of the following represents the total cash flows of an investment, over a period of time, adjusted to reflect the time value of money?
A. The Net Present Value.
B. The Return on Investment.
C. The Time to Payback.
D. The Internal Rate of Return.
正解:A
質問 3:
The term 'happy day' is often used in the context of which of the following investigation techniques?
A. Activity Sampling.
B. Protocol analysis.
C. Document analysis.
D. Scenarios.
正解:D
質問 4:
Which of the following statements is TRUE?
A. Discounted cash flows do not usually take into account the time value of money.
B. It is preferable for the calculated IRR of a project to be below bank interest rates,
C. When comparing two projects, the one with the lower NPV should be preferred.
D. The IRR of every project is based on it achieving a Net Present Value of zero.
正解:D
質問 5:
An analyst has asked a user to describe each step in a task as they perform it.
Which of the following investigation techniques is the analyst using?
A. Activity sampling
B. Interviewing.
C. Ethnographic study.
D. Protocol analysts.
正解:D
質問 6:
When are the acceptance criteria for user acceptance testing defined?
A. When the deliverables of the system design have been agreed.
B. When the software has been completed and has passed system testing
C. When the users have had the opportunity to use the software for a period of time.
D. When the deliverables of the requirements analysis have been agreed.
正解:B
質問 7:
The table below shows the costs and savings associated with a project.
In which of the following years does the project break even?
A. Year 4.
B. Year 3.
C. Year 5.
D. The project does not break even.
正解:C
質問 8:
Which of the following statements about change and change management is correct?
A. Social and cultural factors have little influence on the success of implementing changes.
B. Change management should be considered right from the start of the project.
C. Change management should first be considered in the design stage of the project.
D. The management of change is the sole responsibility of the project manager.
正解:B
相原** -