Cleo is a Project Manager and is drafting a set of objectives for her project. She has decided that the project must have completed stages 1 and 2before the end of the financial year. This is an example of what type of objective?
A. time-bound
B. specific
C. relevant
D. achievable
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
TheTriple Bottom Lineis commonly known as what?
A. people, planet, profit
B. project, people, place
C. place, profit, people
D. project, people, planet
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
When would a company use Value Stream Mapping?
A. to reduce waste
B. to ensure products are value for money for the customer
C. to map the effect of a change
D. to ensure a project runs to timescale
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Frog and Duck Ltd is a new enterprise that has just launched in the technology industry. There are few members of staff and communication is therefore informal. Which phase of growth is Frog and Duck Ltd experiencing?
A. directional evolution
B. co-ordination evolution
C. collaboration evolution
D. creative evolution
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Parker Incorporated is launching a new product which customers will never have seen before. As it is completely unknown to the marketplace, which type of change situation is to be expected?
A. closed change
B. open-ended change
C. contained change
D. predicted change
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
Cleo is a Project Manager and is drafting a set of objectives for her project. She has decided that the project must have completed stages 1 and 2before the end of the financial year. This is an example of what type of objective?
A. time-bound
B. specific
C. relevant
D. achievable
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
Claude is a manager at Sunnyside Ltd and wishes to run a small project in the procurement department. The project will initiate a small incremental change and will have a short timescale. Because of the size of the project Claude doesn't believe he will need to assign an Executive to the project. Is this correct?
A. yes - executives are only required for high-profile or far-reaching projects
B. no - an Executive should still be assigned and communicate regularly
C. yes - executives are only required for long-term projects
D. no - Claude is the Executive of the project
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
Which of the following characteristics of a stakeholder should be considered when conducting a stakeholder analysis for a project?Select THREE
A. Status
B. Money
C. Interest
D. Needs
E. Impact
正解:C,D,E
解説: (Pass4Test メンバーにのみ表示されます)