Which circumstances will allow SUM to run without the creation of a shadow system?
Please choose the correct answer.
Response:
A. Using the main configuration option "Standard" when applying SAP Support Packages
B. Using the database migration option (DMO) for SUM
C. Using the main configuration option "Single System" in case of an upgrade.
D. Using the main configuration option "Single System" when installing an Add-On
正解:D
質問 2:
What do you need to know about the SAP ERP Upgrade and Update Guide?
There are 2 correct answers to this question.
Response:
A. It contains a troubleshooting section
B. It contains a section "free space requirements"
C. It is a database-specific document
D. It is target release specific
正解:B,D
質問 3:
Which are valid options to check the progress of the database migration in a Microsoft Windows environment?
There is correct answers to this question.
Response:
A. Check logs for jobs starting with "RSUPG_SGEN" in the system
B. Check the dump size of the database export on disk
C. Check the log files written under "SUM\abap\log"
D. Check the "Charts Control Center" in the SUM UI
正解:D
質問 4:
You are performing an upgrade with SUM using DMO to an AS ABAP 7.50 based SAP system. You entered a specific number of R3Ioad processes during Roadmap step "Extraction".
Where can you change this during the migration via the Utilities option of the SUM UI?
There are 2 correct answers to this question
Response:
A. In Process Control Center
B. In DMO Migration Preparation
C. In SUM Parameters
D. In SUM Phaselist
正解:A,C