When should an iteration backlog be created?
A. At the beginning of each project.
B. When defining the MBI (Minimum Business Increment).
C. When planning the Kanban board or other put method.
D. At the beginning of each sprint.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
What are the benefits to having a long-live (stable) team?
A. Trustworthy
B. Specifically resourced
C. Ability to multi-task
D. Projectized
E. Highly collaborative
正解:A,E
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
What arc two of the ways that Disciplined Agile provides a solid foundation for business agility? (Choose two)
A. Creates awesome teams that foster joy.
B. Defines a framework foragility at scale.
C. Enforces adherence to organizational standards.
D. Describes the trade-offs associated with a range of options.
E. Provides guidance to streamline processes in a context-sensitive manner.
正解:B,E
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Which phase of the project life cycle develops a consumable solution in a collaborative and incremental manner?
A. Inception
B. Transition
C. Execution
D. Construction
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
What is the purpose of an iteration retrospective?
A. To identity progress and to note encountered impediments.
B. To showcase what the team accomplished in an iteration.
C. To prioritize stories and concrete tasks for the next iteration.
D. To transfer knowledge and improvements to the next iteration.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
Kanetani -
とりあえずこれさえ取得すれば大丈夫です。一般的に通用します。合格することもできました。