The final assembly of a finished product should only be triggered when a customer order arrives.
Which planning strategy for the finished product do you use?
A. Planning without final assembly (strategy 50)
B. Planning with final assembly (strategy 40)
C. Planning with make-to-stock (strategy 10)
D. Planning at the assembly level (strategy 70)
正解:A
質問 2:
Which of the following statements about the SAP Solution Manager listed is correct?
A. Solution Manager is a satellite system in a system landscape.
B. Solution Manager is part of the SAP ECC System.
C. Solution Manager is an add-on industry solution.
D. Solution Manager is a stand-alone system that communicates with other systems in a system landscape.
正解:D
質問 3:
You want to enhance the system statuses of a production order with user statuses.
How do you do this?
A. Define the user statuses in the Customizing table of the system statuses.
B. Define a status profile in Customizing and assign it to the order type.
C. Define the user statuses in the order type-dependent parameters.
D. Define a status profile in Customizing and assign it to the production scheduling profile.
正解:B
質問 4:
Where in the SAP ECC system can you define production versions?
A. In the work center
B. In the material master
C. In the routing
D. In the bill of material
正解:B
質問 5:
Which of the following master data can be used with process orders? (Choose three)
A. Serial numbers
B. Resources
C. Master recipes
D. Production/resource tools
E. Production versions
正解:B,C,E