Where are styles defined and where is style mapping performed?
A. Styles are defined in Microsoft Word
Style mapping is applied in Ariba Contract Management
B. Styles are defined in Ariba Contract Management
Style mapping is applied in Microsoft Word
C. Styles are defined in Ariba Contract Management
Style mapping is applied in Ariba Contract Management
D. Styles are defined in Microsoft Word
Style mapping is applied in Microsoft Word
正解:C
質問 2:
Which types of tasks are available in Ariba Contract Management? Note: There are 3 correct answers to this question
A. Configuration tasks
B. Stage gate tasks
C. To-do tasks (Missed)
D. Review tasks (Missed)
E. Approval tasks (Missed)
正解:C,D,E
質問 3:
Your customer has a signed NDA that is stored within Ariba Contract Management. Now the customer wants to create an agreement for services ... What should the customer do to create the new contract workspace?
A. Create a sub-agreement
B. Create a follow-on project
C. Create a sub-project
D. Copy the NDA workspace
正解:C
質問 4:
Which of the following expressions types can be associated with a condition? Note: There are 3 correct answers to this question
A. Reference to condition (Missed)
B. Team member match
C. Some of
D. Field match (Missed)
E. Any of (Missed)
正解:A,D,E
質問 5:
Which clause type indicates that a user manually edited the clause?
A. Non-Standard
B. Library
C. Ad Hoc
D. Template
正解:A
質問 6:
What is SAP Ariba's recommendation for when to create a sub-agreement to an existing contract? Note: There are 2 correct answers to this question
A. When you add a schedule (Missed)
B. When you apply changes to the language of a contract document
C. When you add a statement of work (Missed)
D. When you renew a contract
正解:A,C
質問 7:
You need to create contract workspaces using the legacy load process. Which CSV file must the customer populate?
A. ContractDocuments.csv
B. ContractLoad.csv
C. Contracts.csv
D. ContractTeam.csv
正解:C
質問 8:
What benefit does your customer have when they include documents in the Contract Workspace template?
A. A user can create contract workspaces from a Sourcing Project template to copy the sourcing documents into that contract workspace
B. Conditions on documents can be copied from the template but can also be created in the individual contract workspace
C. Documents that are added to project templates are included in all contract workspaces created using that template
D. Documents inherited from the template into the contract workspace can be edited or deleted
正解:C