Risk reduction is typically accomplished using:
A. process control
B. changing fluid characteristics
C. results of inspection activities
D. mitigation activities
E. equipment history review
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
A risk assessment requires a cost estimate of potential environmental damage. Vessel replacement cost is
$116,000, and downtime will be 15 days at a cost of $55,000 per day. The EPA fine for a leak of more than
1500 gallons is $1,650,000, and cleanup will cost $1,145,000. What total value will be assigned to the environmental cost of a leak?
A. $3,620,000
B. $1,145,000
C. $1,650,000
D. $2,795,000
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Which of the following would be the minimum expectations of contractors hired to implement an RBI program?
A. Certification in accordance with API RP 580
B. Certification of corrosion/materials specialist to API RP 571
C. Documented training and suitably qualified personnel
D. Documented training in damage mechanisms
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
On a risk plot or matrix, risk thresholds generally divide:
A. various levels of probability of failure.
B. regions of constant risk.
C. various levels of consequence of failure.
D. regions of acceptable and unacceptable risk.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
What is a risk driver?
A. The primary identifier(s) used to assist in the acceptance or mitigation of found damage.
B. The primary element(s) to find, list, and characterize consequence of failure.
C. The primary contributor(s) responsible for a significant share of a risk value.
D. The primary element(s) to find, list, and characterize probability of failure.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
The consequence analysis in an RBI program is performed to:
A. establish on the basis of consequence a relative risk ranking of equipment subject to failure.
B. establish on the basis of consequence a prioritized ranking of equipment items for RBI plans.
C. discriminate between equipment items on the basis of the significance of a potential failure.
D. provide management with numerous options for limiting the consequence of a potential failure.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
Risk assessment is defined as the:
A. process to find, list, and characterize elements of risk.
B. process used to assign values to the probability and consequence of risk.
C. coordinated activities to direct and control risk in an organization.
D. systematic use of information to estimate risk and conduct risk evaluation.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)