A __________ chart is a graphical representation of work left to do versus time.
A. gantt
B. flow
C. bum down
D. pie
正解:C
質問 2:
The most encouraged time of day to hold a Scrum Daily Meeting is:
A. Immediately after lunch
B. 7:00 PM
C. 4:30 PM
D. A beginning of the day
正解:D
質問 3:
According to Scrum, the amount of time for a team to plan Sprint activities is expressed in what unit of time?
A. Minutes
B. Hours
C. Days
D. Weeks
正解:B
質問 4:
Who has the authority to cancel a Sprint?
A. The Scrum Master
B. The team members
C. The Project Manager
D. The Product Owner
正解:D
質問 5:
When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?
A. No, each Scrum Team stands alone
B. No, that is far too hard
C. Yes, but only the Scrum's Teams whose work has dependencies
D. Yes, otherwise Product Owners may not be able to inspect what is done accurately
正解:D
質問 6:
Which of the following is not a Product Owner responsibility?
A. Prioritizing the Product Backlog
B. Working with stakeholders to determine and detail product features
C. Maintaining the Product Backlog with current information
D. Assigning tasks to team members
正解:D