Which of the following contracting methods is typically used when a project requires specific expertise?
A. Competitive bid
B. Lump-sum contract
C. Single-source procurement
D. Subcontracting
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
How should defects be documented in a construction project to effectively evaluate their impact on project quality?
A. Provide more detailed documentation on defects in high-visibility areas.
B. Document all defects and prioritize addressing minor issues first.
C. Focus documentation on issues identified during formal inspections.
D. Create a record that includes the nature, location, and severity of each defect.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
How does the prequalification process impact the project's risk management strategy?
A. It increases the likelihood of contractor preparedness in supporting project outcomes.
B. It enables faster implementation of change orders and continuous assessment of project risks.
C. It facilitates the allocation of resources across project phases.
D. It provides a framework for emergency responses.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
When designing a system to ensure all subcontractors and vendors comply with specific standards relevant to a high-stakes construction project, what elements are crucial to include to guarantee continuous adherence to these standards?
A. Periodically update compliance standards and inform subcontractors and vendors if major changes occur.
B. Focus on internal compliance, trusting subcontractors and vendors to manage their adherence independently.
C. Assume compliance is maintained if no major changes occur throughout the project.
D. Implement a continuous monitoring system that includes scheduled audits and real-time compliance tracking.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
How should input from peer reviews be evaluated during the construction project's design phase?
A. Prioritize feedback from peers based on seniority
B. Assess the applicability of review feedback to enhance design quality
C. Use peer review input to identify who is responsible for the design flaws
D. Focus on feedback that aligns with the project schedule
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
What should be evaluated to ensure that escalation procedures for non-conforming materials are effective in a construction project?
A. The speed with which non-conforming materials are replaced or rectified to maintain project schedule and budget
B. The impact of escalation procedures on public relations, ensuring community support by addressing non-conformances
C. The robustness of the escalation process in identifying, documenting, and resolving non-conformities to prevent recurrence
D. The number of escalations that occur, with fewer escalations indicating success in preventing recurrence
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
What is the most effective way to evaluate areas for improvement identified by CoQ data analysis?
A. Focus improvements on the highest cost and impact areas
B. Assess the root causes of high CoQ areas and determine if improvements align with strategic objectives
C. Prioritize improvements based on ease and speed of implementation
D. Implement random sampling techniques to choose areas for improvement
正解:B
解説: (Pass4Test メンバーにのみ表示されます)