During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13.
What is the velocity of the team?
A. 31
B. 24.5
C. 18
正解:C
質問 2:
A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time.
What would be the elapsed time required to complete the Story?
A. Two days
B. Five hours
C. One day and two hours
正解:C
質問 3:
What is the relationship between the Product Backlog, the Release Backlog and the Sprint Backlog?
A. The Product Backlog is a subset of the Sprint Backlog, which is a subset of the Release Backlog.
B. The Release Backlog is a subset of the Product Backlog, which is a subset of the Sprint Backlog
C. The Sprint Backlog is a subset of the Product Backlog, which is a subset of the Release Backlog.
正解:C
質問 4:
An engineering organization is transforming their project management method to use Agile Scrum.
What is the best approach to the transformation?
A. Get a senior executive to champion the transformation.
B. Make a swift transition and start using Scrum for all projects.
C. Get the team managers to monitor their team's progress on a daily basis.
正解:A
質問 5:
What is a Sprint?
A. A race between two developers to see who can complete a feature fastest.
B. One iteration in the Scrum methodology.
C. A brainstorming session in Extreme programming to generate design ideas.
D. The last iteration in the Scrum project, when the team works long hours to finish the project.
正解:B
質問 6:
What is the best way to split up teams on a large project which is implemented using Scrum?
A. Group by specialty of the team members.
B. Group by features being developed,
C. Group by domain expertise.
正解:B