The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
A. 0.5
B. 0.75
C. 1.33
D. 2
正解:C
質問 2:
Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?
A. Earned value management
B. Activity cost estimates
C. Cost management plan
D. Cost baseline
正解:B
質問 3:
Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?
A. Manage Stakeholder Expectations
B. Plan Risk Responses
C. Define Scope
D. Report Performance
正解:A
質問 4:
Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:
A. Administer Procurements,
B. Close Procurements.
C. Plan Procurements.
D. Conduct Procurements.
正解:A
質問 5:
Plan Risk Management is the process of defining how to:
A. Communicate identified risks to the project stakeholders.
B. Analyze the impact a specific risk may have on the project.
C. Conduct risk management activities for a project.
D. Address unexpected risks that may occur during a project.
正解:C