Which is a purpose of the 'controlling a stage' process?
A. To produce regular highlight reports for the project board
B. To review the success of the project at the end of a management stage
C. To re-plan the current stage and the project when requested
D. To agree work package acceptance and delivery requirements
正解:A
質問 2:
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
A. Executive
B. Project Assurance
C. Project Board
D. Corporate group
正解:D
質問 3:
Which is a purpose of the Controlling a Stage process?
A. Assign work to be done and take corrective action to ensure that the stage remains within tolerance
B. Enable the organization to understand the work that needs to be done to deliver the project's products
C. Provide a fixed reference point at which acceptance for the project product is confirmed
D. Enable the Project Board to be provided with sufficient information to authorize the next stage
正解:A
質問 4:
What is an advantage of applying the 'learn from experience' principle?
A. It allows the project team to identify improvements to be made during the project
B. It allows the project team to fully understand their roles and responsibilities
C. It allows the project manager to delegate time tolerances to the team managers
D. It allows the project board to delegate cost tolerances to the project manager
正解:A
質問 5:
Identify the missing words in the following sentence.
The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.
A. the project board has agreed the project strategies
B. the 'starting up a project' process is completed
C. the project mandate has been approved by the project board
D. corporate, programme management or the customer have authorized a project
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
How does the project board use the 'manage by stages' principle to control the project?
A. By ensuring that the benefits are managed and controlled
B. By reviewing project viability at defined intervals
C. By reviewing previous project closure documentation
D. By approving the project management team
正解:B