Which is a purpose of an End Project Report?
A. Ensure that key project information is archived and made secure
B. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
C. Review how well the project performed against the Project Initiation Documentation used to authorize it
D. Identify individuals or groups that need to be told that the project is coming to an end
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
What statement describes how the project manager should ensure effective communication within a project?
A. Rely on regular reporting by team managers to determine whether the work Is on track
B. Involve 3 small group of key stakeholders when defining the project to reduce the amount of communication
C. Use a more structured approach to communication with co-located teams, then remote teams
D. Focus on publishing standard messages to key influencers throughout the project
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Which is a benefit of using PRINCE2?
A. Is a method specifically designed for technical projects
B. Includes many of the proven planning techniques, such as critical path analysis
C. Can be used to manage both projects and programmes
D. Provides for the efficient and economic use of management time
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Which is a purpose of the plans theme?
A. To identify, assess and control any potential changes to the baseline
B. To establish the project's structure of accountability
C. To understand whether the targets are achievable
D. To assess and control uncertainty
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Which term is defined as the result of change, normally affecting real-world behaviour and circumstances?
A. Outcome
B. Benefit
C. Request for change
D. Output
正解:A