Factory calendars are assigned to the maintenance plant and work center.
By default, which factory calendar is used for work order scheduling?
A. Planning plant
B. Production work center linked to a technical object
C. Main work center
D. Maintenance plant
正解:C
質問 2:
In order costing configuration, for what is the allocation structure used?
A. To determine the cost elements that are allowed in the plant maintenance order
B. To allocate costs to a hierarchy of maintenance technical objects
C. To determine the settlement receiving elements for costs debited to the order
D. To provide a method of consolidating costs in the Plant Maintenance Information System
正解:C
質問 3:
When a user creates a notification or an order and enters a functional location as the reference object, you want the system to suggest the subordinate equipment automatically.
In addition to setting the reference object view in the order or the notification, what other settings must you make?(Choose two)
A. Set the Equipment-Installation Allowed indicator in the Functional Location master data record.
B. Set the Single Installation indicator in the equipment master data record.
C. Set View Profiles for Technical Objects in Customizing.
D. Set the Single Installation indicator in the Functional Location master data record.
正解:A,D
質問 4:
In Customizing, to what data must you assign digital signatures in addition to the order type?
A. Planning plant
B. Work center
C. Maintenance planner group
D. Maintenance plant
正解:A
質問 5:
Your customer wants to utilize estimated costs in Plant Maintenance orders.
Which condition does the customer need to be aware of?
A. Planned costs must not exceed the estimated costs.
B. A specific order type in which cost estimates are activated must be used.
C. Planned costs overwrite estimated costs after release of the order.
D. Upon release of the order, estimated costs cannot be revised.
正解:D
質問 6:
Your customer wants to generate costing for internal activities.
For which of the following can you define various rates in Activity Type/Price Planning transaction?(Choose three)
A. Plant
B. Value category
C. Plan/actual version
D. Cost center
E. Period
正解:C,D,E