What is the focus of a SCRUM of SCRUMS in an Agile Context?
A. Best Practice adoption
B. Communication to the Project Management Office
C. Integration Topics
D. Backlog Management
正解:C
質問 2:
Working in an Agile approach, what should your planning look like at the Beginning of the realize phase?
A. User stories are in a ready state for NO more than the first three sprints
B. Timelines of the sprint may differ due to the workload
C. Project scope and planning are completed and final
D. Go-live scope is fixed on the first of January the following year
正解:A
質問 3:
What are some responsibilities of the steering committee during implementation of an SAP S/4HANA Cloud project?
A. Act as a multiplier within your organization to train and support end users.
B. Maintain responsibilities for users in your company.
C. Ensures the resources necessary for the project's success are available.
D. Responsible for inspection and approval of results and of the overall project.
E. Last escalation level for problems (conflict management).
正解:C,D,E
質問 4:
Which of the following statements about Scrum is correct? Please choose the correct answer.
A. The three ceremonies are sprint planning, daily scrum, sprint review (retrospective).
B. In Scrum, as best practices, we have three main roles, and three artifacts or three ceremonies.
C. Scrum Master defines and prioritizes features and gathers requirements.
D. In Scrum, the team is Self-organized, define all task necessary for all project life cycle.
正解:A
質問 5:
What does "SSCUI" stand for?
A. Self-Service Customization User Interface
B. Self-Service Configuration User Interface
C. Self-Service Collection User Interface
D. Self-Service Creation User Interface
正解:B
質問 6:
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition. What is the correct sequence of selected key deliverables across the project phases?
Please choose the correct answer.
Response:
A. a) Production Readiness Check
b) Detailed system Assessment
c) Code Adjustment
d) Validation of Migration
B. a) Code adjustment
b) Detailed System Assessment
c) Production Readiness Check
d) Validation of Migration
C. a) Detailed system Assessment
b) Code Adjustment
c) Validation of Migration
d) Production Readiness Check
D. a) Detailed system Assessment
b) Production Readiness Check
c) Code Adjustment
d) Validation of Migration
正解:C