Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
A. Project Integration Management
B. Project Scope Management
C. Project Communications Management
D. Project Information Management System (PIMS)
正解:C
質問 2:
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
A. Finish-to-finish (FF).
B. Start-to-start (SS).
C. Start-to-finish (SF).
D. Finish-to-start (FS).
正解:D
質問 3:
After Define Activities and Sequence Activities, the next process is:
A. Control Schedule.
B. Estimate Activity Durations,
C. Estimate Activity Resources.
D. Develop Schedule.
正解:C
質問 4:
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
A. Human resource plan
B. Quality management plan
C. Procurement management plan
D. Communications management plan
正解:D
質問 5:
One of the objectives of a quality audit is to:
A. offer assistance with non-value-added activities.
B. share the process documentation among stakeholders.
C. highlight the need for root cause analysis.
D. identify all of the gaps or shortcomings.
正解:D
Nara -
きっちりと情報がまとまっているし読みやすいです。APM-001知識も経験も無しにいきなりこの試験から受けるという方はいないでしょうし、これで十分だとは思いますが。