Which is a type of issue?
A. A request for change
B. An Exception Report
C. A lesson
D. A risk with an estimated high impact
正解:A
質問 2:
Within which integrated element does PRINCE2 set minimum requirements?
A. Project environment
B. Processes
C. Themes
D. Principles
正解:C
質問 3:
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
A. Techniques
B. Processes
C. Themes
D. Principles
正解:D
質問 4:
Which is a purpose of an End Project Report?
A. Ensure that key project information is archived and made secure
B. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
C. Review how well the project performed against the Project Initiation Documentation used to authorize it
D. Identify individuals or groups that need to be told that the project is coming to an end
正解:C
質問 5:
How does the project plan help to support the 'manage by stages' principle?
A. By defining products to ensure they are fit for purpose
B. By estimating the timescales and costs of the project
C. By identifying the major control points and milestones
D. By identifying the customer's quality expectations
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
Which product identifies how often stakeholders require information?
A. Change control approach
B. Communication management approach
C. Quality management approach
D. Risk management approach
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
Which is a recommended quality review team role?
A. Project Support
B. Administrator
C. Assurance
D. Project Manager
正解:B
質問 8:
Which process provides information for the project board to review a completed stage and confirm continued business justification?
A. Directing a project
B. Closing a project
C. Managing a stage boundary
D. Controlling a stage
正解:C
解説: (Pass4Test メンバーにのみ表示されます)