If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
A. Executive
B. Senior Supplier
C. Senior User
D. Corporate/programme management
正解:D
質問 2:
Which is a typical core activity within configuration management?
A. Issue management
B. Preparation
C. Quality inspection
D. Quality inspection
正解:D
質問 3:
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
A. project cost tolerance
B. product cost tolerance
C. stage cost tolerance
D. Work Package cost tolerance
正解:D
質問 4:
Why is the Initiating a Project process used?
A. To enable corporate or programme management to give authorization to deliver a project
B. To fully understand how the project objectives will be achieved before committing significant resources
C. To decide which project approach is suitable for the project
D. To produce the required Work Packages
正解:B
質問 5:
Which should be provided by corporate or programme management before the Starting up a Project process commences?
A. The Project Initiation Documentation
B. Authority to initiate a project
C. Sufficient information to identify the prospective Executive
D. A Project Brief
正解:C
質問 6:
Which is a benefit of using PRINCE2?
A. Enables a Project Manager to be accountable for the success of a project
B. Provides a defined structure of accountability, delegation, authority and communication
C. Includes techniquesfor critical path analysis and earned value analysis
D. Prevents any changes once the scope of a project has been agreed
正解:B
質問 7:
Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.
A. minimum necessaryis done to decide if a project is worthwhile
B. Project Brief is assembled and approved
C. project approach appropriate for delivering a project is selected
D. aim is to establish sound foundations to achieve a successful project
正解:D