Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?
A. Business Case
B. Plans
C. Progress
D. Quality
正解:C
質問 2:
Identify the missing word(s) in the following sentence. Quality assurance provides assurance to the [?] that the project is being conducted appropriately whilst Project Assurance provides the same assurance to all the project's stakeholders.
A. Executive
B. corporate or programme management organization
C. Project Manager
D. Suppliergroups
正解:B
質問 3:
What is described as an organization's unique attitude towards risk taking?
A. Risk appetite
B. Risk management
C. Risk tolerance
D. Risk evaluation
正解:A
質問 4:
Which should be provided by a project mandate?
A. Terms of reference
B. Stage tolerances
C. Initiation Stage Plan
D. Detailed Business Case
正解:A
質問 5:
In what process is the authorization to deliver the project's products given?
A. Initiating a Project
B. Managing a Stage Boundary
C. Directing a Project
D. Starting up a Project
正解:C
質問 6:
Where should the names of those who are to approve a product be recorded?
A. Configuration Item Record
B. Product Status Account
C. Checkpoint Report
D. Product Description
正解:D
質問 7:
Which product identifies the management stages and timescales of a project?
A. Project Product Description
B. Project Plan
C. Initiation Stage Plan
D. Project Brief
正解:B