Which of following best defines Outcomes?
A. New operational state achieved after transition of capability in live operations
B. Measurable improvement resulting from outcomes perceived as advantage
C. Completed set of project outputs
D. Deliverable of a project
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
The Smart Meter Programme is in Tranche 2 and the Customer Processes Project is delivering ahead of schedule. This means that fewer resources are required to complete the project. The Training Project, which was due to start in Tranche 3, has now become a higher priority and needs to be started early. The programme manager has recommended starting the Training Project now although Tranche 2 and Tranche 3 will then overlap.
Is this an appropriate application of the structure' theme, and why?
A. No, because tranches should remain sequential if overlapping the tranches would increase the risks to programme delivery
B. Yes, because tranches may overlap if the programme is making good progress and capability is available
C. Yes, because available resource capacity should be fully utilized throughout the programme
D. No, because tranches should be sequential to enable end-of-tranche reviews to take place before the next tranche is approved
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
The CFO has been appointed as the SRO for the Smart Meter Programme.
Is this appointment an appropriate application of the 'organization' theme, and why?
A. Yes, because the CFO can direct the programme, providing new insights as they are new to UU
B. Yes, because the CFO is able to monitor whether the increase in customers and reduction in costs is achieved
C. No, because the CFO has no previous experience or working knowledge of the utility industry operations
D. No, because the CEO, who has industry knowledge, is better qualified to develop the programme vision
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
At the start of the programme, the programme manager listed some design-related actions to be completed.
Which role is MOST focused on each task?

正解:

Explanation:
Design Action
Role
Show the vision statement to the engineering and maintenance staff and collect feedback from them Business change manager Facilitate the recruitment of a consultant to help the CTO assess new call centre technologies Programme manager Agree to the use of external consultants to help build the target operating model Senior responsible owner The BCM is responsible for the interface between the programme and the business (staff feedback). The Programme Manager handles the day-to-day operational facilitation and procurement support. The SRO has the ultimate authority to approve significant resource expenditures like external consultancies.
質問 5:
The project team working on the Training Project in Tranche 3 needs to understand the new processes and knowledge required by staff members to develop a coherent set of training materials. The project team also needs to know the skills and qualifications for each role, and any new processes. The project manager is concerned that some of the documentation provided is outdated and does not now reflect the current processes being developed.
Which aspect of information management, if applied correctly, is MOST LIKELY to address these concerns?
A. Access control
B. Storage
C. Integrity
D. Version control
正解:D
解説: (Pass4Test メンバーにのみ表示されます)