You want to add a report to the side panel of the item detail screen. The new report should display the upto-date financial planning values for the item.
Which reporting tool do you use?
A. Business Context Viewer (BCV)
B. Evaluation
C. BI report
D. Portfolio dashboard
正解:A
質問 2:
You want to confirm your work hours to tasks with the cross-Application time sheet (SAP CATS). When you enter the time sheet (CAT2) your list is empty.
What could be the reason for this?
NOTE: There are 2 correct answers to this question.
A. Your role and business partner are assigned to task that have the created status
B. Your role and business partner are assigned to tasks that have the in process status
C. Your user is not assigned to a business partner
D. Your personal number is not assigned to a business partner
正解:A,D
質問 3:
Which method can you use to update multiple values simultaneously in capacity planning for portfolio management?
A. Drag and drop
B. Mass update
C. XML upload
D. Distribution function
正解:D
質問 4:
Resources are not shown in the Resource Overview
What is the reason for this?
NOTE: There are 2 correct answers to this question
A. Project response assignment
B. Resource pool assignment is missing
C. Staffing manager assignment is missing
D. Assignment of resource management authorization object is missing
正解:B,C
質問 5:
You have defined an item template. When you create a new item, you notice that you cannot select the template.
What could be the reason for this?
NOTE: There are 2 correct answers to this question
A. The item template has a different item type
B. The item template is not available in the selected bucket
C. The item template has the Activate status
D. The item template start date is in the future
正解:A,B
質問 6:
You are in portfolio management and create a project system (PS) project from an item.
Which parts you add afterwards directly in PS?
NOTE: There are 3 correct answers to this question
A. Network activities
B. Network components
C. PS texts
D. WBS elements
E. Documents
正解:A,C,E
質問 7:
You have created a role in project management but the role is not displayed on the fast entry screen.
What could be the reason for this?
A. The role has the staffing in process status
B. The role has the staffing in preparation status
C. The flexible Assignment indicator is active in role type customizing
D. The Distribution indicator is active role type customizing
正解:B