Assume that the following test cases have been executed at the end of the first week of test execution: TC-001, TC-002 and TC-007. All these tests are 'passes'.
What is the MINIMUM number of the remaining test cases that must be successfully executed to fulfill the EX1 exit criteria?

Number of correct responses: 1
K32 credits
A. 4
B. 5
C. 6
D. 7
正解:A
質問 2:
Improving the Testing Process
Consider the following statements describing the importance of improving the test process:
I. Test process improvement is important because being focused only on the test process it can provide recommendations to improve the test process itself, but it can't indicate or suggest improvement to areas of the development process II. Test process improvement is important because it is much more effective than software process improvement to improve the quality of a software system III. Test process improvement is important because several process improvement models (STEP, TPI Next, TMMi) have been developed over the years IV. Test process improvement is important because every organization, regardless of the context, should always achieve the maximum level of maturity of testing described in the test improvement models such as TMMi Which of the following answers is correct?
Number of correct responses: 1
K21 credit
A. I., II., III. and IV are false
B. I., II. and III are true; IV. is false
C. I. and IV. are true; II. and III. are false
D. I., II. and III. are false; IV. is true
正解:A
質問 3:
The test team is using a distributed model for testing.
What is the primary factor you should consider with this model? [1]
A. Planned vs. actual hours
B. Provision of growth opportunities for the individual testers
C. Co-location of test team
D. Alignment of methodologies
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
What is the primary use for the traceability information regarding the relationship between test results and test conditions during test execution? [2]
A. The development manager uses this information to determine how many developer resources to allocate to defect repair.
B. The tester uses this information to determine which test should be run next.
C. The Test Manager uses this information to control the test execution effort.
D. The project manager uses this information to determine if the project is on schedule.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Improving the Testing Process
Which of the following statements about the TMMi test process improvement model is true?
Number of correct responses: 1
K21 credit
A. TMMi provides an approach for test process improvement such as the IDEAL (Initiating, Diagnosing, Establishing, Acting and Learning) model
B. At TMMi level 1 testing is chaotic without a defined process, and it is often seen as the same as debugging
C. TMMi has a staged architecture for process improvement with seven maturity levels
D. In TMMi all the process areas at lower levels must be 75% complete by achieving specific and generic goals in order to claim the higher level
正解:B