You are the manager of a test team. You inherited most of these people from a previous manager who promoted technical skills, particularly programming skills. As a result, your people are very strong in test automation skills, white box testing and complex test design techniques. You have just been told that you can hire five new people. You want the new people to complement the existing skill sets and you want to be sure the team will have a strong mutual respect.
Given the following options, who should you hire? [3]
A. Hire college interns who can be trained by the existing people.
B. Hire all black box testers because you are severely lacking in that skill set.
C. Hire a mix of people with strong testing and domain skills.
D. Hire customer support people who have experience with the customer interface.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Test Management
Based on the historical data of 5 past and similar projects, you have calculated these average numbers of defects detected in system testing:
- for each 10000 LOC (lines of code), 200 defects
- for each person-month of development team effort, 49 defects
You want to use this information to perform estimation for a new project.
The project manager tells you that he/she has estimated 20000 new LOC for this new project.
Four developers work for four months on this project before system testing.
During system testing, 797 defects are discovered.
Assume that the system test of this new project is using the same amount of work as spent in the past projects.
Based on this information only, which of the following statement is certainly true about this project?
Number of correct responses: 1
K33 credits
A. More LOC than planned have been delivered to system testing with a higher defect density than the past projects
B. The number of defects found during the system test phase on the new project is approximately proportional to the development team effort
C. The code for the new project contains a higher defect density than the code of the past projects
D. 40000 LOC have been delivered to system testing (against the 20000 LOC planned by the project manager)
正解:B
質問 3:
You are managing a project that will be using a model-based testing strategy.
Which of the following is an activity that will be needed in order to implement this strategy? [1]
A. Create the test charters for the exploratory testing sessions.
B. Conduct a quality risk analysis with all affected stakeholders.
C. Conduct operational profiling to determine the expected usage of the system.
D. Select an appropriate quality standard, such as ISO 9126, to be used to guide the testing.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Your company just won a contract to create a new sales application and has committed to a very aggressive delivery timeline. Due to the quick turnaround your primary stakeholder wants to be heavily involved in the design and is very anxious to see the outcome. Because of this, your company has decided to use a spiral development approach. You have a defined test policy and typically use an analytical approach to testing, however, this approach will not work with the development approach.
What test strategy should be utilized? [3]
A. Methodical
B. Reactive
C. Standard-compliant
D. Model-based
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
The Test Manager must assemble team members that have which of the following characteristics? [1]
A. Will not change the severity of a defect report
B. Thrive in a routine, structured environment
C. Will spark informal cross training among themselves
D. Possess identical skill sets
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
Test Management
Which one of the following metrics to be produced needs traceability between the test cases and each item in a proper test basis?
Number of correct responses: 1
K21 credit
A. Trends in the lag time from defect reporting to resolution
B. Requirements coverage
C. Cumulative number of reported defects versus cumulative number of resolved defects
D. Mean time between failures for the system
正解:B
質問 7:
You are the Test Manager of a risk-based testing effort. You develop the following graph to show residual risk. Assume that "Risks mitigated" represents passed tests and "Risks not mitigated" represents failed tests and other discovered failures.
Which of the following answers best represents what the graph shows? [3]
A. Project is behind schedule based on bug fix rate
B. Project is ahead of schedule due to number of risks addressed
C. Project is on schedule based on total number of test cases executed
D. Project is at risk due to the number of failed tests
正解:D
解説: (Pass4Test メンバーにのみ表示されます)