Which option correctly presents the main characteristics of test estimation?
A. Time - Cost - Quality
B. Quality - Cost - Effort
C. Time - Cost - Effort
D. Time - Effort - Quality
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
You just handed over the Defect Accepted and Deferred report to your Maintenance team.
Which testing activity are you performing? [1]
A. Test Decommission
B. Test Exit Criteria
C. Test Closure
D. Defect Design
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
You are the Test Manager on a project to replace an old sales and merchandising system with one that will be based on modern platforms.
The main requirements for the system are:
* Loading sales data, sent electronically from the stores each evening, into a central database.
* Producing sales reports for the merchandisers.
* Producing forecast reports, used to predict demand.Loading sales data and producing reports with the current system has frequently taken longer than the overnight processing window allows. The Data Centre Manager requires that all batch processing takes at least 10% less time than currently.The Sales and Merchandising Manager is more concerned about usability because the parameter entry will be complex.Which option contains two key considerations that would need to be added to your test approach?
A. Usability testing in pre-prod by the team; performance efficiency testing in pre-prod too
B. Usability testing during system testing and acceptance testing in pre-prod; performance testing in pre- prod
C. Usability testing during system testing; performance efficiency testing post system test phase
D. Full user experience testing in a model office lab and load testing on user parameter entry
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
You are the Test Manager for a software house (SoftTech), who provide a core banking product to retail banks around the world to enable their customers to process payments via the Internet and telephone banking.
Your current project is to integrate SoftTech's core banking product with Welsh Bank's existing bank systems.
However, Welsh Bank's systems are maintained by experienced developers and are poorly documented.
Welsh Bank has stated that this project must comply with Financial Conduct Authority (FCA) regulatory banking standards.
A specification for the 10 interfaces to Welsh Bank's existing systems has been produced by SoftTech's development team.
You have been asked to plan and conduct reviews for the system integration and support documentation of all the systems. Which of the following is the BEST approach for this project?
SELECT ONE OPTION
A. Conduct an audit to verify that all test deliverables have been produced and signed off.
B. Conduct an informal review of the integration documentation before the systems are integrated.
C. Conduct a management review to assess progress of the integration features.
D. Conduct Inspections to verify that all documentation conforms to a set standard.
正解:D
質問 5:
Which one of the following options would help ensure success in using an Exploratory Testing approach?
SELECT ONE OPTION
A. Exploratory test sessions are time boxed and have a test charter that only experienced test analysts can execute.
B. Exploratory test sessions produce test charters that are executed after all functional testing is complete.
C. Exploratory test sessions produce test charters that provide a detailed set of instructions for the novice tester to follow.
D. Exploratory test sessions are time boxed and have a test charter stating the test conditions to be covered.
正解:D
質問 6:
Your company just won a contract to create a new sales application and has committed to a very aggressive delivery timeline. Due to the quick turnaround your primary stakeholder wants to be heavily involved in the design and is very anxious to see the outcome. Because of this, your company has decided to use a spiral development approach. You have a defined test policy and typically use an analytical approach to testing, however, this approach will not work with the development approach.
What test strategy should be utilized?
A. Methodical
B. Reactive
C. Standard-compliant
D. Model-based
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
The test team is using a distributed model for testing.
What is the primary factor you should consider with this model? [1]
A. Planned vs. actual hours
B. Provision of growth opportunities for the individual testers
C. Co-location of test team
D. Alignment of methodologies
正解:D
解説: (Pass4Test メンバーにのみ表示されます)