Which of the following decides whether networks can be header assigned or activity-assigned?
There are 2 correct answers to this question.
Response:
A. Plant
B. Network structure
C. Billing type
D. Order type
正解:A,D
質問 2:
For which objects can billing plans be created? (2)
A. Activities
B. Sales order items
C. WBS elements
D. Milestones
E. Project definition
正解:B,C
質問 3:
Which scenario does not allow you to access the project team of the higher-level WBS element during
"workforce planning"?
Please choose the correct answer.
Response:
A. If a WBS element does not have its own project team
B. Project team is in the higher level in hierarchy to WBS element
C. If a WBS element does have its own project team
D. WBS element is in the higher level
正解:C
質問 4:
Which of the following statements about milestone billing are correct?
There are 3 correct answers to this question.
Response:
A. The revenue value of the sales order item can be assigned to dates in the billing plan.
B. For each billing date in a billing plan, you can define whether the date is fixed or whether it is moved along with the dates of the milestone.
C. The amount to be billed is entered directly in the milestones of the WBS elements or activities.
D. If a milestone is to be used as a date in a billing plan, the "Sales document date" indicator must be activated in the milestone.
E. The billing block on a billing date is removed when the related milestone is confirmed with an actual date.
正解:A,B,E
質問 5:
What do you call a closed sequence of relationships and activities where you start from an activity and end up back at the same activity, by way of relationships?
Please choose the correct answer.
Response:
A. Cycle
B. Cycle analysis
C. Web structures
D. Graphics
正解:A
質問 6:
What are the components on which reporting is based upon, in profit center accounting?
There are 2 correct answers to this question.
Response:
A. Cost elements
B. Profit centers
C. Profit center hierarchy
D. Cost centers
正解:B,C
かわ** -
C_TPLM22_67問題の解説部分でも語句説明が丁寧なのでインプットもしやすい点も良いと思います。