Among the various functions provided by progress tracking that simplify data entry and analysis which function allows you to go the master data display for objects that are underlined?
Please choose the correct answer.
Response:
A. Subitems
B. Copying dates
C. Mass change of scenarios
D. Hotspots
正解:D
質問 2:
Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board.
What is the status that must be set before you can enter actual start and actual end dates?
There are 2 correct answers to this question.
Response:
A. Partially released
B. Released
C. Partially set
D. Partially finished
正解:A,B
質問 3:
What do you choose when creating a new network by copying an operative network?
There are 3 correct answers to this question.
Response:
A. Relationships
B. PS texts
C. WBS elements
D. Milestones
正解:A,B,D
質問 4:
In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.
How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?
Please choose the correct answer.
Response:
A. Costing key is considered
B. System uses valuation variant
C. The system uses the key from the work center
D. The costs are distributed evenly over the earliest dates in the activity
正解:C
質問 5:
In your project, you choose internal activities to confirm actual dates. After you partially confirmed an internal activity, you want that the actual start will be considered for the calculation of the earliest scheduled dates.How can you implement this?
Please choose the correct answer.
Response:
A. Deactivate actual date consider indicator in Parameters for Network Scheduling.
B. Activate the shift order indicator in Parameters for Network Scheduling.
C. Activate the actual date consider indicator in Parameters for Network Scheduling.
D. Deactivate the shift order indicator in Parameters for Network Scheduling.
正解:D
質問 6:
Which of the following are controlled using plant and order type parameters?
There are 2 correct answers to this question.
Response:
A. Number assignment
B. The settlement rule strategy
C. Default value settings
D. If the network is assigned to an activity or header
正解:B,D