Which describes a risk event?
A. The derivation or sources of a potential risk to the project
B. The achievement of a milestone on the Project Plan
C. The area of uncertainty in terms of the threat or opportunity
D. The sequence of events and actions that will be put in place if a risk occurs
正解:C
質問 2:
Which is shown in a product breakdown structure?
A. What resources are required to develop the products
B. The major products that are to be developed in a plan
C. In which order the products should be created
D. Management stages, major products and control points
正解:B
質問 3:
Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?
A. End Project Report
B. End Stage Report
C. Product Status Account
D. Checkpoint Report
正解:B
質問 4:
Where should an off-specification be recorded?
A. Risk Register
B. Issue Register
C. Work Package
D. Configuration Management Strategy
正解:B
質問 5:
Which is a purpose of a Configuration Management Strategy?
A. Define how the products and their versions will be identified
B. Define whether a project will use a risk budget
C. Identify who will set up the Quality Register
D. Provide a record of each configuration item and any important relationships between them
正解:A
質問 6:
What product identifies the management stages and other major control points in a project?
A. Business Case
B. Project Plan
C. Work Package
D. Project Brief
正解:B
質問 7:
Identify the missing word in the following sentence, A project's output is produced during a project but the [?] for the project are often only realized after the project has closed.
A. issues
B. costs
C. benefits
D. risks
正解:C
質問 8:
Which is a purpose of the Controlling a Stage process?
A. Update a Project Plan to incorporate the actuals from a Stage Plan
B. Produce a Team Plan for the work to be assigned to a Team Manager
C. Obtain approvals for products delivered in a Work Package
D. Select and implement actions that will resolve deviations from a plan within tolerance
正解:D
質問 9:
When should the Project Board refer to corporate or programme management for a decision?
A. The stage requires resources
B. It is forecast that project level tolerance will be exceeded
C. The Senior Supplier or Senior User needs to be changed
D. Any request for change needs to be approved
正解:B