Which is a responsibility of the managing level within the project management team?
A. Appoint the project management team
B. Ensure that the products are produced within the constraints agreed with the Project Board
C. Approve stage completion
D. Set project tolerances
正解:B
質問 2:
Which is shown in a product breakdown structure?
A. What resources are required to develop the products
B. The major products that are to be developed in a plan
C. In which order the products should be created
D. Management stages, major products and control points
正解:B
質問 3:
Which describes risk impact?
A. The effect of the risk on the delivery of project objectives
B. The trigger that occurred giving rise to the risk
C. Timeframe within which the risk might occur
D. How likely the risk is to occur in a given project situation
正解:A
質問 4:
Upon what environment is PRINCE2 based?
A. Programme
B. Operational
C. Customer/supplier
D. Configuration
正解:C
質問 5:
Which describes risk probability?
A. Level of risks which the project can tolerate before escalating to the Project Board
B. A measure of the likelihood of the risk occurring
C. Probable effect on the project delivering its objectives
D. Timeframe within which the risk may occur
正解:B
質問 6:
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
A. Project Plan
B. End Stage Report
C. Work Package
D. Team Plan
正解:A
質問 7:
Which of the following is NOT an event-driven control?
A. Project mandate
B. Exception Report
C. Checkpoint Report
D. End of a stage
正解:C
質問 8:
Which of the following describes a use of a Configuration Item Record?
A. Identify the techniques and procedures required within the Work Package
B. Define the identification scheme to be applied to the project
C. Record the reporting requirements for the Work Package
D. Record the change in a product's status
正解:D
1069 お客様のコメント
クリック」





相*岬 -
Pass4Testは100%の品質保証を提供している。全額返金する保証と品質高い問題集を持っています。本当に役に立ちました!